Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address NEW:
2126 S ALVERNON WY
Apply Date:
09/16/2024
Applicant:
BORDER TRAFFIC SAFETY BEN LOZANO
Description:
installation of conduit infrastructure to facilitate installation of fiber optic cabling for the city of Tucson

Permit Reviews

Permit Number - TR-ROW-0924-01057
Permit Status: Complete
Permit Description: installation of conduit infrastructure to facilitate installation of fiber optic cabling for the city of Tucson
Start Date Submittal Complete Date Status  
09/16/2024 RIGHT-OF-WAY REVIEW v.1 09/19/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0924-01057
Permit Status: Complete
Permit Description: installation of conduit infrastructure to facilitate installation of fiber optic cabling for the city of Tucson
Total Outstanding Activity Conditions - 3
Date Name
09/18/2024 MULTIPLE JURIDSICTIONS
09/18/2024 PRE-CON/PAVEMENT/SIDEWALK
09/18/2024 Traffic control set-up approved between 9AM - 3:30PM

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0924-01057
Permit Description: installation of conduit infrastructure to facilitate installation of fiber optic cabling for the city of Tucson
Total Completed Inspections - 3
Date Description Inspector Results Comments
10/01/2024 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed reviewed work hours and traffic control set up, returning today to inspect TCP
10/18/2024 TRSP - ROW - Backfill - Placement/Compaction Passed potholes backfilled and patched
10/21/2024 TRSP - ROW - Final Passed all work completed, job site cleaned