Permit Details

Status:
Inspections
Type:
Right-of-Way (ROW)
Address:
7659 E 42ND ST
Address NEW:
7659 E 42ND ST
Apply Date:
08/18/2026
Applicant:
Alexis Otero-Morales
Description:
New Sewer main with 2 new manholes in street related to new subdivision. 10/07/2026 - Request for 30 Day Renewal as of 10/30/2026

Permit Reviews

Permit Number - TR-ROW-0826-00905
Permit Status: Inspections
Permit Description: New Sewer main with 2 new manholes in street related to new subdivision. 10/07/2026 - Request for 30 Day Renewal as of 10/30/2026
Start Date Submittal Complete Date Status  
08/18/2026 RIGHT-OF-WAY REVIEW v.1 08/25/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0826-00905
Permit Status: Inspections
Permit Description: New Sewer main with 2 new manholes in street related to new subdivision. 10/07/2026 - Request for 30 Day Renewal as of 10/30/2026
Total Outstanding Activity Conditions - 5
Date Name
08/20/2026 Traffic Control set-up approved between 7AM - 5PM
08/20/2026 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
08/20/2026 UNDER A PAVEMENT MORATORIUM, ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES.
08/20/2026 Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online.
08/20/2026 PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING.

Completed Inspections

Permit Status: Inspections
Permit Number: TR-ROW-0826-00905
Permit Description: New Sewer main with 2 new manholes in street related to new subdivision. 10/07/2026 - Request for 30 Day Renewal as of 10/30/2026
Total Completed Inspections - 3
Date Description Inspector Results Comments
09/01/2026 Passed first day of mobilization. traffic control in place for roadway closure with active 811 marks in excavation area.
08/31/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed on site meeting with Paul, reviewed scope of work, job duration, and restoration. Planning on setting up traffic control tomorrow.
10/06/2026 Passed

Documents

File Name Document Type  
COT - TR - ROW PERMIT (SSRS).PDF DOCUMENTS VIEW
JWCIVIL8-TCP_V1.PDF DOCUMENTS VIEW
P26SC00013-CARSON SEWER - APPROVED-SITE PLAN_V1.PDF DOCUMENTS VIEW