Permit: TR-ROW-0426-00423
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW)
Address:
8502 E GOLF LINKS RD
Address NEW:
8502 E GOLF LINKS RD
Apply Date:
04/13/2026
Applicant:
Benjamin Lozano - Border Traffic Safety LLC
Description:
Deck joint replacement for the bridge on E Golf Links Rd over the Pantano Wash.
Permit Reviews
Permit Number - TR-ROW-0426-00423
Permit Status: Inspections
Permit Description: Deck joint replacement for the bridge on E Golf Links Rd over the Pantano Wash.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/21/2026 | RIGHT-OF-WAY REVIEW v.2 | 04/21/2026 | APPROVED |
| 04/13/2026 | RIGHT-OF-WAY REVIEW v.1 | 04/21/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0426-00423
Permit Status: Inspections
Permit Description: Deck joint replacement for the bridge on E Golf Links Rd over the Pantano Wash.
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 04/14/2026 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRTIVE MANUAL **Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 – 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 04/14/2026 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
| 04/14/2026 | Traffic control set-up approved between 9AM - 3:30PM |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-ROW-0426-00423
Permit Description: Deck joint replacement for the bridge on E Golf Links Rd over the Pantano Wash.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/23/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | first phase of joint replacement has started, barricade set up will be inspected in reoccurring phases for each lane closure switch | |
| 05/29/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | Final phase for bridge joints, traffic control set up in place. Aiming for final pour and cleanup on Wednesday 6/10. | |
| 07/16/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | all bridge joints completed, and flush with existing grade | |
| 07/16/2026 | TRSP - ROW - Final | Passed | all joints on bridge have been completed, job site is clear of all traffic control devices, approved |