Inspection Status: Complete (Recurring)
Inspection History: TRSP - ROW - Barricade - Setup/Routine
| Date |
Description |
Inspector |
Results |
Comments |
| 04/23/2026 |
TRSP - ROW - Barricade - Setup/Routine |
|
Complete (Recurring) |
outer eastbound lanes closed for first phase of project, will have reoccurring inspections for inner and westbound lane closures |
| 05/04/2026 |
TRSP - ROW - Barricade - Setup/Routine |
|
Complete (Recurring) |
phase 2 tcp setup in place, 2 left EB lanes closed for joint replacement. Advanced warnings and channeling devices in place. |
| 05/18/2026 |
TRSP - ROW - Barricade - Setup/Routine |
|
Complete (Recurring) |
phase 3 of joint replacement is in effect. Early warning and arrow board signs for westbound travel lanes are posted, channeling devices to taper traffic to one lane. Jose from Sun Tran has been notified that current Sun Tran bus stop is inaccessible, he will be setting up a temporary bus stop later today. |
| 05/29/2026 |
TRSP - ROW - Barricade - Setup/Routine |
|
Passed |
Final phase for bridge joints, traffic control set up in place. Aiming for final pour and cleanup on Wednesday 6/10. |