Permit: TR-ROW-0424-00482
Permit Details
Apply Date:
04/25/2024
Applicant:
Jim Morrison
Description:
Connection to TEP (for development package) in City ROW.
Permit Reviews
Permit Number - TR-ROW-0424-00482
Permit Status: Complete
Permit Description: Connection to TEP (for development package) in City ROW.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/25/2024 | RIGHT-OF-WAY REVIEW v.1 | 04/29/2024 | REQUIRES RESUBMIT |
05/02/2024 | RIGHT-OF-WAY REVIEW v.2 | 05/03/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0424-00482
Permit Status: Complete
Permit Description: Connection to TEP (for development package) in City ROW.
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
04/25/2024 | Traffic control set-up approved between 9AM - 3:30PM |
04/26/2024 | PRE-CON/PAVEMENT/SIDEWALK |
05/02/2024 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0424-00482
Permit Description: Connection to TEP (for development package) in City ROW.
Total Completed Inspections - 3
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/16/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | work schedule unknown at this time. Jim will call when ready | |
08/05/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | new permit opened | |
09/18/2024 | TRSP - ROW - Final/Close-Out | Passed | permit expired, job continuing on new permit |