Permit: TR-ROW-0424-00392
Permit Details
Apply Date:
04/09/2024
Applicant:
Jim Morrison
Description:
CONTINUATION OF TR-ROW-0124-00003" Directional Bore Under S Kolb Rd for new Water line. Work associated with development package TD-DEV-0323-00170
Permit Reviews
Permit Number - TR-ROW-0424-00392
Permit Status: Complete
Permit Description: CONTINUATION OF TR-ROW-0124-00003" Directional Bore Under S Kolb Rd for new Water line. Work associated with development package TD-DEV-0323-00170
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/09/2024 | RIGHT-OF-WAY REVIEW v.1 | 04/11/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0424-00392
Permit Status: Complete
Permit Description: CONTINUATION OF TR-ROW-0124-00003" Directional Bore Under S Kolb Rd for new Water line. Work associated with development package TD-DEV-0323-00170
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
04/09/2024 | ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. ** PAVEMENT PATCH TYPE SHALL BE IN CONFORMANCE TO THE CURRENT EDITION OF THE CITY OF TUCSON PUBLIC UTILITY ADMINISTRATIVE MANUAL. **SIDEWALK CLOSED AHEAD SIGNS SHALL BE PLACED AT THE NEAREST ADA ACCESS RAMPS PER MUTCD CHAPTER 6D. |
04/09/2024 | Traffic control set-up approved between 9AM - 3:30PM |
05/14/2024 | ROW Permit is only allowed for City of Tucson Limits. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-0424-00392
Permit Description: CONTINUATION OF TR-ROW-0124-00003" Directional Bore Under S Kolb Rd for new Water line. Work associated with development package TD-DEV-0323-00170
Total Completed Inspections - 6
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/18/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
05/24/2024 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
05/24/2024 | TRSP - ROW - SITE INSPECTION | Passed | ||
06/06/2024 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
06/07/2024 | TRSP - ROW - Barricade Takedown | Passed | ||
06/10/2024 | TRSP - ROW - Final/Close-Out | Passed | site restored and completed |