Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address NEW:
831 E LIMBERLOST DR
Apply Date:
01/17/2025
Applicant:
Andrew Ruiz
Description:
Replace pavement to centerline of Limberlost after shutting valve off. Please refer to TR-ROW-1224-01399. And we are going to access an existing manhole per the requirements of Sewer plan G-2023-048 - no digging or trenching

Permit Reviews

Permit Number - TR-ROW-0125-00090
Permit Status: Complete
Permit Description: Replace pavement to centerline of Limberlost after shutting valve off. Please refer to TR-ROW-1224-01399. And we are going to access an existing manhole per the requirements of Sewer plan G-2023-048 - no digging or trenching
Start Date Submittal Complete Date Status  
01/27/2025 RIGHT-OF-WAY REVIEW v.2 01/27/2025 APPROVED Review Details
01/17/2025 RIGHT-OF-WAY REVIEW v.1 01/23/2025 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-0125-00090
Permit Status: Complete
Permit Description: Replace pavement to centerline of Limberlost after shutting valve off. Please refer to TR-ROW-1224-01399. And we are going to access an existing manhole per the requirements of Sewer plan G-2023-048 - no digging or trenching
Total Outstanding Activity Conditions - 2
Date Name
01/23/2025 PRE-CON/PAVEMENT/SIDEWALK
01/23/2025 Traffic control set-up approved between 9AM - 3:30PM

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-0125-00090
Permit Description: Replace pavement to centerline of Limberlost after shutting valve off. Please refer to TR-ROW-1224-01399. And we are going to access an existing manhole per the requirements of Sewer plan G-2023-048 - no digging or trenching
Total Completed Inspections - 3
Date Description Inspector Results Comments
01/29/2025 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed
02/25/2025 TRSP - ROW - Barricade - Setup/Routine Passed
02/25/2025 TRSP - ROW - Final Passed