Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TR-ROW-0124-00061
Permit Details
Apply Date:
01/11/2024
Applicant:
Ben Hager
Description:
Updated - 5/01/2024 - Overhead crane work and large loads access points on Right-of- Way. To place large concrete slabs on the roof of High rise building. Park Ave: - Closure to all Sidewalks, Bike Lanes, and Drive Lanes from June 3rd at 5:00AM to June 14th at 5:00pm to allow for safe operating space. 6/3/2024 (5:00am ) - 6/14/2024 (5:00pm) J H Findorff & Son Inc. will be the Contractor responsible for the work, ROC # 328650. Updated - 4/09/2024 -- Revision for Night Work- " Revising permit for Overnight pours in Late April & Early May per provided and approved TNE. No Changes to Existing TCP.. TNE Dates - April 19th with backup dates of April 18th & 22nd, April 25th with backup dates of April 24th & April 26th ; May 6th with backup dates of May 3rd & May 7th, starting at 1 am and continuing until Sunrise on the following day. 3/19/2024 - Revising permit for overnight pours in late March and Early April per provided and approved TNE. No changes to existing TCP. -- New Night work dates - March 25th with backup dates of March 22nd & 26th, April 1st with backup dates of March 29th & April 2nd, April 8th with backup dates of April 5th & 8th, April 25th with back up dates of April 12th & 16th, starting at 1 am and continuing until Sunrise.. Original - Full road closure- Continuation of TR-ROW-0823-01028 which expired 01-07-2024 (with renewal) Overnight concrete pours 01-16-2024: TNE for January 23rd with January 22nd and 24th as backup dates AND January 30th with January 29th and 31st as backup dates if needed, starting at 1am and continuing until Sunrise on the following day. notes from previous permit TR-ROW-0823-01028: **** UPDATED - Park Ave: - Closure to all Sidewalks, Bike Lanes, and Drive Lanes from 5:00AM - 3:00PM the to allow for safe operating space of the Telebelt Material Placement Machine to safely Operate. In addition, on the 9/25 and 9/29 closures, we will also be testing the (3) new manholes that were installed this summer with Pima County. Duration of the work will be the following days: 9/25/23 from 5AM to 3PM 9/29/23 from 5AM to 3PM 10/6/23 from 5AM to 3PM... ***** Overnight Closure of Park Ave for concrete pour associated with DP20-0152 on Thursday, August 10, 2023 at 6:00am. Additional dates include Sundays August 13th and 27th from 11pm through sunrise the following day 12/6/23 Revised TNE - December 7th with backup dates of December 6th OR 8th and December 20th with backup dates of December 19th OR 21st starting at 1am and continuing until Sunrise 12/22/23 -full closure per approved TCP for December 20, 2023 through January 4, 2024 to perform onsite work while students are out of school. Approved TNE for January 2, 2024 with back up dates of December 29th, 2023 or January 3rd, 2024 starting at 1AM and continuing through sunrise. 01/02/2024- (TNE) January 9, 2024 with back up dates of January 8th OR January 10th, 2024 starting at 1am and continuing until Sunrise on the following day.
Permit Reviews
Permit Number - TR-ROW-0124-00061
Permit Status: Issued
Permit Description: Updated - 5/01/2024 - Overhead crane work and large loads access points on Right-of- Way. To place large concrete slabs on the roof of High rise building.
Park Ave: - Closure to all Sidewalks, Bike Lanes, and Drive Lanes from June 3rd at 5:00AM to June 14th at 5:00pm to allow for safe operating space.
6/3/2024 (5:00am ) - 6/14/2024 (5:00pm)
J H Findorff & Son Inc. will be the Contractor responsible for the work, ROC # 328650.
Updated - 4/09/2024 -- Revision for Night Work- " Revising permit for Overnight pours in Late April & Early May per provided and approved TNE. No Changes to Existing TCP.. TNE Dates - April 19th with backup dates of April 18th & 22nd, April 25th with backup dates of April 24th & April 26th ; May 6th with backup dates of May 3rd & May 7th, starting at 1 am and continuing until Sunrise on the following day.
3/19/2024 - Revising permit for overnight pours in late March and Early April per provided and approved TNE. No changes to existing TCP. -- New Night work dates - March 25th with backup dates of March 22nd & 26th, April 1st with backup dates of March 29th & April 2nd, April 8th with backup dates of April 5th & 8th, April 25th with back up dates of April 12th & 16th, starting at 1 am and continuing until Sunrise..
Original - Full road closure- Continuation of TR-ROW-0823-01028 which expired 01-07-2024 (with renewal) Overnight concrete pours
01-16-2024: TNE for January 23rd with January 22nd and 24th as backup dates AND January 30th with January 29th and 31st as backup dates if needed, starting at 1am and continuing until Sunrise on the following day.
notes from previous permit TR-ROW-0823-01028:
**** UPDATED - Park Ave: - Closure to all Sidewalks, Bike Lanes, and Drive Lanes from 5:00AM - 3:00PM the to allow for safe operating space of the Telebelt Material Placement Machine to safely Operate. In addition, on the 9/25 and 9/29 closures, we will also be
testing the (3) new manholes that were
installed this summer with Pima County.
Duration of the work will be the following days:
9/25/23 from 5AM to 3PM
9/29/23 from 5AM to 3PM
10/6/23 from 5AM to 3PM... ***** Overnight Closure of Park Ave for concrete pour associated with DP20-0152 on Thursday, August 10, 2023 at 6:00am. Additional dates include Sundays August 13th and 27th from 11pm through sunrise the following day
12/6/23 Revised TNE - December 7th with backup dates of December 6th OR 8th and December 20th with backup dates of December 19th OR 21st starting at 1am and continuing until Sunrise
12/22/23 -full closure per approved TCP for December 20, 2023 through January 4, 2024 to perform onsite work while students are out of school. Approved TNE for January 2, 2024 with back up dates of December 29th, 2023 or January 3rd, 2024 starting at 1AM and continuing through sunrise.
01/02/2024- (TNE) January 9, 2024 with back up dates of January 8th OR January 10th, 2024 starting at 1am and continuing until Sunrise on
the following day.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/09/2024 | RIGHT-OF-WAY REVIEW v.1 | 02/13/2024 | APPROVED |
01/23/2024 | RIGHT-OF-WAY REVIEW v.2 | 01/24/2024 | REQUIRES RESUBMIT |
03/19/2024 | RIGHT-OF-WAY REVIEW v.1 | 03/25/2024 | APPROVED |
01/26/2024 | RIGHT-OF-WAY REVIEW v.3 | 02/01/2024 | APPROVED |
05/02/2024 | RIGHT-OF-WAY REVIEW v.2 | 05/03/2024 | APPROVED |
04/30/2024 | RIGHT-OF-WAY REVIEW v.1 | 05/01/2024 | REQUIRES RESUBMIT |
04/09/2024 | RIGHT-OF-WAY REVIEW v.1 | 04/15/2024 | APPROVED |
02/21/2024 | RIGHT-OF-WAY REVIEW v.1 | 02/27/2024 | APPROVED |
01/12/2024 | RIGHT-OF-WAY REVIEW v.1 | 01/22/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-ROW-0124-00061
Permit Status: Issued
Permit Description: Updated - 5/01/2024 - Overhead crane work and large loads access points on Right-of- Way. To place large concrete slabs on the roof of High rise building.
Park Ave: - Closure to all Sidewalks, Bike Lanes, and Drive Lanes from June 3rd at 5:00AM to June 14th at 5:00pm to allow for safe operating space.
6/3/2024 (5:00am ) - 6/14/2024 (5:00pm)
J H Findorff & Son Inc. will be the Contractor responsible for the work, ROC # 328650.
Updated - 4/09/2024 -- Revision for Night Work- " Revising permit for Overnight pours in Late April & Early May per provided and approved TNE. No Changes to Existing TCP.. TNE Dates - April 19th with backup dates of April 18th & 22nd, April 25th with backup dates of April 24th & April 26th ; May 6th with backup dates of May 3rd & May 7th, starting at 1 am and continuing until Sunrise on the following day.
3/19/2024 - Revising permit for overnight pours in late March and Early April per provided and approved TNE. No changes to existing TCP. -- New Night work dates - March 25th with backup dates of March 22nd & 26th, April 1st with backup dates of March 29th & April 2nd, April 8th with backup dates of April 5th & 8th, April 25th with back up dates of April 12th & 16th, starting at 1 am and continuing until Sunrise..
Original - Full road closure- Continuation of TR-ROW-0823-01028 which expired 01-07-2024 (with renewal) Overnight concrete pours
01-16-2024: TNE for January 23rd with January 22nd and 24th as backup dates AND January 30th with January 29th and 31st as backup dates if needed, starting at 1am and continuing until Sunrise on the following day.
notes from previous permit TR-ROW-0823-01028:
**** UPDATED - Park Ave: - Closure to all Sidewalks, Bike Lanes, and Drive Lanes from 5:00AM - 3:00PM the to allow for safe operating space of the Telebelt Material Placement Machine to safely Operate. In addition, on the 9/25 and 9/29 closures, we will also be
testing the (3) new manholes that were
installed this summer with Pima County.
Duration of the work will be the following days:
9/25/23 from 5AM to 3PM
9/29/23 from 5AM to 3PM
10/6/23 from 5AM to 3PM... ***** Overnight Closure of Park Ave for concrete pour associated with DP20-0152 on Thursday, August 10, 2023 at 6:00am. Additional dates include Sundays August 13th and 27th from 11pm through sunrise the following day
12/6/23 Revised TNE - December 7th with backup dates of December 6th OR 8th and December 20th with backup dates of December 19th OR 21st starting at 1am and continuing until Sunrise
12/22/23 -full closure per approved TCP for December 20, 2023 through January 4, 2024 to perform onsite work while students are out of school. Approved TNE for January 2, 2024 with back up dates of December 29th, 2023 or January 3rd, 2024 starting at 1AM and continuing through sunrise.
01/02/2024- (TNE) January 9, 2024 with back up dates of January 8th OR January 10th, 2024 starting at 1am and continuing until Sunrise on
the following day.
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
01/18/2024 | The following extended traffic control set-up times were approved: 24 Hrs |
02/26/2024 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
03/22/2024 | Plan review applications expire 180 days from date of submittal unless the permit has been issued. Permits expire 180 days after issuance or last approved inspection. |
Completed Inspections
Permit Status: Issued
Permit Number: TR-ROW-0124-00061
Permit Description: Updated - 5/01/2024 - Overhead crane work and large loads access points on Right-of- Way. To place large concrete slabs on the roof of High rise building.
Park Ave: - Closure to all Sidewalks, Bike Lanes, and Drive Lanes from June 3rd at 5:00AM to June 14th at 5:00pm to allow for safe operating space.
6/3/2024 (5:00am ) - 6/14/2024 (5:00pm)
J H Findorff & Son Inc. will be the Contractor responsible for the work, ROC # 328650.
Updated - 4/09/2024 -- Revision for Night Work- " Revising permit for Overnight pours in Late April & Early May per provided and approved TNE. No Changes to Existing TCP.. TNE Dates - April 19th with backup dates of April 18th & 22nd, April 25th with backup dates of April 24th & April 26th ; May 6th with backup dates of May 3rd & May 7th, starting at 1 am and continuing until Sunrise on the following day.
3/19/2024 - Revising permit for overnight pours in late March and Early April per provided and approved TNE. No changes to existing TCP. -- New Night work dates - March 25th with backup dates of March 22nd & 26th, April 1st with backup dates of March 29th & April 2nd, April 8th with backup dates of April 5th & 8th, April 25th with back up dates of April 12th & 16th, starting at 1 am and continuing until Sunrise..
Original - Full road closure- Continuation of TR-ROW-0823-01028 which expired 01-07-2024 (with renewal) Overnight concrete pours
01-16-2024: TNE for January 23rd with January 22nd and 24th as backup dates AND January 30th with January 29th and 31st as backup dates if needed, starting at 1am and continuing until Sunrise on the following day.
notes from previous permit TR-ROW-0823-01028:
**** UPDATED - Park Ave: - Closure to all Sidewalks, Bike Lanes, and Drive Lanes from 5:00AM - 3:00PM the to allow for safe operating space of the Telebelt Material Placement Machine to safely Operate. In addition, on the 9/25 and 9/29 closures, we will also be
testing the (3) new manholes that were
installed this summer with Pima County.
Duration of the work will be the following days:
9/25/23 from 5AM to 3PM
9/29/23 from 5AM to 3PM
10/6/23 from 5AM to 3PM... ***** Overnight Closure of Park Ave for concrete pour associated with DP20-0152 on Thursday, August 10, 2023 at 6:00am. Additional dates include Sundays August 13th and 27th from 11pm through sunrise the following day
12/6/23 Revised TNE - December 7th with backup dates of December 6th OR 8th and December 20th with backup dates of December 19th OR 21st starting at 1am and continuing until Sunrise
12/22/23 -full closure per approved TCP for December 20, 2023 through January 4, 2024 to perform onsite work while students are out of school. Approved TNE for January 2, 2024 with back up dates of December 29th, 2023 or January 3rd, 2024 starting at 1AM and continuing through sunrise.
01/02/2024- (TNE) January 9, 2024 with back up dates of January 8th OR January 10th, 2024 starting at 1am and continuing until Sunrise on
the following day.
Total Completed Inspections - 2
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/16/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
12/12/2024 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed |