Permit: TF-FCP-0323-00455
Permit Details
Apply Date:
03/08/2023
Applicant:
Jackie Lovett
Description:
In response to UPS needs at existing facility, install new above ground fuel storage tank skid with dispensers and new concrete pad to be connected to existing infrastructure.
Permit Reviews
Permit Number - TF-FCP-0323-00455
Permit Status: Complete
Permit Description: In response to UPS needs at existing facility, install new above ground fuel storage tank skid with dispensers and new concrete pad to be connected to existing infrastructure.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/08/2023 | FIRE CONSTRUCTION REVIEW v.1 | 03/08/2023 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TF-FCP-0323-00455
Permit Description: In response to UPS needs at existing facility, install new above ground fuel storage tank skid with dispensers and new concrete pad to be connected to existing infrastructure.
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/16/2023 | COT - FCON - Tank - Final | Passed | Closed by mistake, re-opening this permit and waiting for Final Inspection notice. This is for the fueling center on west side of facility. Tank is in place but not ready for Final Inspection. 3/25/2024 Passed on the condition that NFPA Diamond and "Unleaded Fuel" Label would be installed. |