Permit: TD-DEV-1224-00327
Permit Details
Apply Date:
12/06/2024
Applicant:
Vance Goodman
Description:
AT-RISK ROUGH GRADING PERMIT ONLY for Sequoia Apartments and Parking Lot
Permit Reviews
Permit Number - TD-DEV-1224-00327
Permit Status: Stop work order
Permit Description: AT-RISK ROUGH GRADING PERMIT ONLY
for Sequoia Apartments and Parking Lot
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
12/06/2024 | DEVELOPMENT PACKAGE NEW v.1 | 12/17/2024 | APPROVED |
Outstanding Inspections
Permit Status: Stop Work Order
Permit Number: TD-DEV-1224-00327
Permite Description: AT-RISK ROUGH GRADING PERMIT ONLY
for Sequoia Apartments and Parking Lot
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/31/2024 | NPPO Pre-Construction | N/A | Re-inspection required | Contractors not on site this morning |
01/14/2025 | N/A | Partial Pass | Contractor has started clearing and grubbing and rough grading. But not on site at this time. | |
01/14/2025 | SITE - Stormwater Setup and Controls | N/A | Re-inspection required | contractor has not set up the track out rock or Wattles |
Completed Inspections
Permit Status: Stop Work Order
Permit Number: TD-DEV-1224-00327
Permit Description: AT-RISK ROUGH GRADING PERMIT ONLY
for Sequoia Apartments and Parking Lot
Total Completed Inspections - 2
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/19/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | I informed the contractor that we needed all third-party testing starting as January one 2025. Contractor needs to install wattles on the south side of the project. Calling for inspection for swap inspection stormwater inspections, biweekly. | |
01/06/2025 | NPPO Pre-Construction | Passed | Contractor will contact CoT for inspection of NPPO nursery when the plants are moved and protected on-site. |