Permit: TD-DEV-1222-00091
Permit Details
Status:
Issued
Type:
Development Package
Address:
2320 N SILVERBELL RD
Address NEW:
2320 N SILVERBELL RD
Apply Date:
12/23/2022
Applicant:
Lisa Bowers
Description:
New Drive-thru lane
Permit Reviews
Permit Number - TD-DEV-1222-00091
Permit Status: Issued
Permit Description: New Drive-thru lane
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/27/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 02/01/2023 | REQUIRES RESUBMIT |
| 02/15/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 02/23/2023 | REQUIRES RESUBMIT |
| 03/07/2023 | DEVELOPMENT PACKAGE REVIEW v.3 | 04/03/2023 | APPROVED |
Outstanding Inspections
Permit Status: Issued
Permit Number: TD-DEV-1222-00091
Permite Description: New Drive-thru lane
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/21/2024 | PDSD Site/Engineering Division - NPPO | N/A | Not Applicable | |
| 03/21/2024 | COT - ENGR - Stormwater | N/A | Not Ready | Provide water harvesting as shown |
| 03/21/2024 | SITE - Stormwater Setup and Controls | N/A | Not Ready | Please provide stormwater controls as needed, including concrete containment |
| 03/21/2024 | PDSD Engineering Division Pre-Construction SITE | N/A | Not Ready | Construction has started without preconstruction meeting. There’s no personnel or activity on site at this time. Please schedule inspections from development package permit as required. |
| 04/04/2024 | SITE | N/A | Partial Pass | Water and electrical utility work in progress |
| 04/04/2024 | PDSD Site/Engineering Division - Landscaping | N/A | Partial Pass | Trees are protected in place |
| 04/04/2024 | Final inspection to ensure all landscape and water harvesting SITE | N/A | Not Applicable | |
| 04/04/2024 | SITE - SWPPP Violation Notice | N/A | Not Applicable | |
| 05/03/2024 | SITE - Stormwater Follow-up | N/A | Partial Pass | construction debris and other garbage throughout the site |
| 01/22/2026 | ENGR Engineering Final | N/A | Not Ready | Completed work is not in compliance with approved development package. Issues noted below. 1. New ADA access isle is not 8 feet wide 2. New ADA parking signage is missing 3. New ADA curb ramp running slope is greater than 8.33% (measured at 11.35%) 4. New pedestrian circulation across drive-through lane has cross-slope greater than 2% 5. Island at south-east corner was not removed, PAAL width is less than 24 feet at this point 6. 6 inch curb along drive-through lane was not installed 7. Curb ramp and striping for pedestrian circulation to trash enclosure were not installed 8. Long-term bicycle parking is not installed 9. Self-closing gates do not self close |
| 07/23/2026 | Consultation SITE | N/A | Partial Pass | Discussed site issues and options. Further discussion required prior to submission of revised plan. |
Completed Inspections
Permit Status: Issued
Permit Number: TD-DEV-1222-00091
Permit Description: New Drive-thru lane
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/03/2024 | ENGR - Drainage Structures | Passed |