Permit: TD-DEV-0823-00364
Permit Details
Apply Date:
08/17/2023
Applicant:
Brandy Burke
Description:
*Revision 2 started 10/2/2024 (shift access drive, widen ADA ramp landing, added traffic control sign) , Revision #1 started 3/18/24 (utility modifications)* New Restaurant with Drive-thru, being Salad and Go.
Permit Reviews
Permit Number - TD-DEV-0823-00364
Permit Status: Complete
Permit Description: *Revision 2 started 10/2/2024 (shift access drive, widen ADA ramp landing, added traffic control sign) , Revision #1 started 3/18/24 (utility modifications)* New Restaurant with Drive-thru, being Salad and Go.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/27/2024 | AS-BUILT v.1 | 07/15/2024 | REQUIRES RESUBMIT |
08/09/2024 | AS-BUILT v.2 | 08/29/2024 | REQUIRES RESUBMIT |
08/18/2023 | DEVELOPMENT PACKAGE NEW v.1 | 09/27/2023 | REQUIRES RESUBMIT |
03/18/2024 | DEVELOPMENT PACKAGE NEW v.1 | 04/10/2024 | APPROVED |
01/19/2024 | DEVELOPMENT PACKAGE NEW v.4 | 02/05/2024 | APPROVED |
10/23/2023 | DEVELOPMENT PACKAGE NEW v.2 | 11/21/2023 | REQUIRES RESUBMIT |
10/02/2024 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 10/25/2024 | APPROVED |
11/30/2023 | DEVELOPMENT PACKAGE NEW v.3 | 01/04/2024 | REQUIRES RESUBMIT |
06/10/2024 | AS-BUILT v.1 | 06/24/2024 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-0823-00364
Permite Description: *Revision 2 started 10/2/2024 (shift access drive, widen ADA ramp landing, added traffic control sign) , Revision #1 started 3/18/24 (utility modifications)* New Restaurant with Drive-thru, being Salad and Go.
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/03/2024 | ENGR - Drainage Structures | N/A | Not Applicable | There is no drainage. Structural on this site. |
07/26/2024 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | The contractor has scheduled this meeting to meet on site and discuss two issues that they have for this project. The first issue is the water harvesting located at the south east corner of this project and the existing tree in the same vicinity that they are trying to save. I have advised them to check with Chad Keller in the office and see what his determination would be to save that tree as shown on the plans, but not be able to provide the water harvesting. The second concern for this site is the modification of the plans at the north west corner for the new driveway and all the existing power poles and communication equipment in that area. I have advised them to contact Stephen blood and look at the plans and see what they will need to do to modify this area and get it approved on the revised drawings. |
07/26/2024 | SITE - Zoning Compliance | N/A | Not Ready | The contractor has scheduled this meeting to meet on site and discuss two issues that they have for this project. The first issue is the water harvesting located at the south east corner of this project and the existing tree in the same vicinity that they are trying to save. I have advised them to check with Chad Keller in the office and see what his determination would be to save that tree as shown on the plans, but not be able to provide the water harvesting. The second concern for this site is the modification of the plans at the north west corner for the new driveway and all the existing power poles and communication equipment in that area. I have advised them to contact Stephen blood and look at the plans and see what they will need to do to modify this area and get it approved on the revised drawings. |
11/06/2024 | COT - SITE - Zoning Intermediate | N/A | Partial Pass | Discussed ADA issues at back door and provided options for compliance. |
11/27/2024 | SITE | N/A | Not Applicable | See Chad Keller inspection comments. |
11/27/2024 | Final inspection to ensure all landscape and water harvesting SITE | N/A | Re-inspection required | 1. Remove soil/rock mulch next to the light pole in the planting area to the east of the drive-thru lane to allow overflow drainage to reach the north portion of the basin. 2. Remove the Palo Verde that is obstructing the view of the stop sign at the drive-thru lane. Move the Palo Verde to the street landscape border where trees are not present and move one of the Red Yucca to the stop sign area where the Palo Verde was removed. |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0823-00364
Permit Description: *Revision 2 started 10/2/2024 (shift access drive, widen ADA ramp landing, added traffic control sign) , Revision #1 started 3/18/24 (utility modifications)* New Restaurant with Drive-thru, being Salad and Go.
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/22/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | ||
07/18/2024 | PDSD Site/Engineering Division - Landscaping | Passed | contractor has not started on any of the landscaping | |
07/26/2024 | City of Tucson (COT) Planning and Development Services Engineering (ENGR) Zoning Compliance Inspection | Passed | The contractor has scheduled this meeting to meet on site and discuss two issues that they have for this project. The first issue is the water harvesting located at the south east corner of this project and the existing tree in the same vicinity that they are trying to save. I have advised them to check with Chad Keller in the office and see what his determination would be to save that tree as shown on the plans, but not be able to provide the water harvesting. The second concern for this site is the modification of the plans at the north west corner for the new driveway and all the existing power poles and communication equipment in that area. I have advised them to contact Stephen blood and look at the plans and see what they will need to do to modify this area and get it approved on the revised drawings. |
|
08/29/2024 | Consultation SITE | Passed | Discussed was the drive lane changes, bike parking and water harvesting areas. Plan will be submitted as a revision today the 29th of August. | |
11/26/2024 | For trash and recycling enclosures | Passed | ||
12/16/2024 | ENGR Engineering Final | Passed | ||
12/16/2024 | COT - ENGR - Signage Final | Passed | ||
12/16/2024 | Final inspection to ensure all landscape and water harvesting SITE | Passed |