Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TD-DEV-0723-00310
Permit Details
Apply Date:
07/14/2023
Applicant:
Description:
Take 5 Oil Change Facility
Permit Reviews
Permit Number - TD-DEV-0723-00310
Permit Status: Inspections
Permit Description: Take 5 Oil Change Facility
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/21/2024 | DEVELOPMENT PACKAGE NEW v.1 | 11/26/2024 | REQUIRES RESUBMIT |
| 07/01/2025 | DEVELOPMENT PACKAGE NEW v.2 | 07/22/2025 | APPROVED |
| 07/14/2023 | DEVELOPMENT PACKAGE NEW v.1 | 08/24/2023 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0723-00310
Permite Description: Take 5 Oil Change Facility
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/12/2025 | For trash and recycling enclosures | N/A | Partial Pass | 12/12/25 Footer dimensions and reinforcing correct. Bollard footers correct. Footer okay to pour. Request inspection for pregrout when wall is built per plan and ready with bond beam at top. Use ladders horizontal reinforcement at 16" oc. |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0723-00310
Permit Description: Take 5 Oil Change Facility
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/10/2025 | PDSD Engineering Division Pre-Construction SITE | Passed |
Scheduled Inspections
Scheduled Inspections - TD-DEV-0723-00310
Status: Inspections
Description: Take 5 Oil Change Facility
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| 12/19/2025 | For trash and recycling enclosures | Scheduled |
For information about today’s scheduled inspections please refer to the
PDSD Daily Inspections Dashboards (Desktop)
PDSD Daily Inspections Dashboards (Mobile)
.