Permit: TD-DEV-0623-00269
Permit Details
Apply Date:
06/07/2023
Applicant:
Fabien Reille
Description:
*Revision #1 started 2/6/24 * 1) Procuring and installing One (1) 25' Non Light pole behind Guard Shack. 2) Install concrete foundation as specified. 3) Procure and Install conduit from GS to Camera. 4) Procure and install CAT6 cable for cameras. 5) Install Amazon procured Camera n Pole/building.
Permit Reviews
Permit Number - TD-DEV-0623-00269
Permit Status: Complete
Permit Description: *Revision #1 started 2/6/24 * 1) Procuring and installing One (1) 25' Non Light pole behind Guard Shack. 2) Install concrete foundation as specified. 3) Procure and Install conduit from GS to Camera. 4) Procure and install CAT6 cable for cameras. 5) Install Amazon procured Camera n Pole/building.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/10/2023 | DEVELOPMENT PACKAGE NEW v.2 | 08/09/2023 | REQUIRES RESUBMIT |
02/06/2024 | DEVELOPMENT PACKAGE NEW v.1 | 03/25/2024 | APPROVED |
08/16/2023 | DEVELOPMENT PACKAGE NEW v.3 | 09/12/2023 | REQUIRES RESUBMIT |
09/14/2023 | DEVELOPMENT PACKAGE NEW v.4 | 10/09/2023 | APPROVED |
06/08/2023 | DEVELOPMENT PACKAGE NEW v.1 | 06/09/2023 | REQUIRES RESUBMIT |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0623-00269
Permit Description: *Revision #1 started 2/6/24 * 1) Procuring and installing One (1) 25' Non Light pole behind Guard Shack. 2) Install concrete foundation as specified. 3) Procure and Install conduit from GS to Camera. 4) Procure and install CAT6 cable for cameras. 5) Install Amazon procured Camera n Pole/building.
Total Completed Inspections - 4
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/17/2024 | SITE - Zoning Final | Passed | ||
11/18/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | This job has been completed and is CO Ready. | |
11/18/2024 | ENGR Engineering Final | Passed | This job has been completed and is CO Ready. | |
11/18/2024 | COT - FCON - Fire - Final | Passed |