Permit: TD-DEV-0524-00155
Permit Details
Apply Date:
05/22/2024
Applicant:
Blake Junak
Description:
New commercial building for Valvoline gas station
Permit Reviews
Permit Number - TD-DEV-0524-00155
Permit Status: Inspections
Permit Description: New commercial building for Valvoline gas station
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/27/2024 | DEVELOPMENT PACKAGE NEW v.3 | 08/29/2024 | APPROVED |
| 05/24/2024 | DEVELOPMENT PACKAGE NEW v.1 | 07/11/2024 | REQUIRES RESUBMIT |
| 07/24/2024 | DEVELOPMENT PACKAGE NEW v.2 | 08/23/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TD-DEV-0524-00155
Permit Status: Inspections
Permit Description: New commercial building for Valvoline gas station
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/02/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0524-00155
Permite Description: New commercial building for Valvoline gas station
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/10/2025 | NPPO Monitoring | N/A | Partial Pass | Contractor that needs to replace all the dead trees in the nursery area |
| 11/10/2025 | N/A | Not Ready | contractor has not started the grading on the drive-through or the parking area | |
| 12/02/2025 | ENGR Engineering Final | N/A | Not Ready | Contractor still needs a complete all the landscaping area and finish paving |
| 12/01/2025 | ENGR Paving | N/A | Partial Pass | I was on site early this morning and the contractor was not ready. So I came back at 12 PM to check the AB grade. Everything looks good for payment tomorrow morning. |
| 12/02/2025 | N/A | Partial Pass | Contractor needs to install all the sidewalks covers from the downspout of the roof | |
| 09/12/2025 | For trash and recycling enclosures | N/A | Partial Pass | Footing dimensions and reinforcement are correct. Okay to pour footing. Okay to proceed with metal screen wall per approved building plans (TC-COM-0524-01012) |
| LAND Landscape Appearance & Function Final | N/A | Requested | ||
| NPPO Final | N/A | Requested | ||
| COT - ENGR - Signage Final | N/A | Requested |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0524-00155
Permit Description: New commercial building for Valvoline gas station
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/03/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | NPPO all needs to be retagged, completed to,early and most tags are missing, no NPPO nursery area noted on plan. NPPO inspection will be completed after pip plants are tagged and nursery location decided. | |
| 04/15/2025 | NPPO Pre-Construction | Passed | Off-site nursery location approved for TOS tree #8. This is the only plant being preserved. No on-site nursery necessary. Plant will be brought back when ready for final location. |