Permit: TD-DEV-0423-00208
Permit Details
Status:
Issued
Type:
Development Package
Address:
8181 S CAMINO DE CAFE
Address NEW:
8181 S CAMINO DE CAFE
Apply Date:
04/10/2023
Applicant:
Chris Guinter
Description:
New building with parking and landscaping improvements
Permit Reviews
Permit Number - TD-DEV-0423-00208
Permit Status: Issued
Permit Description: New building with parking and landscaping improvements
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/20/2023 | DEVELOPMENT PACKAGE NEW v.1 | 07/19/2023 | REQUIRES RESUBMIT |
| 07/19/2023 | DEVELOPMENT PACKAGE NEW v.2 | 12/28/2023 | APPROVED |
| 04/11/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 06/06/2023 | REQUIRES RESUBMIT |
| 05/06/2026 | AS-BUILT v.1 | 05/14/2026 | APPROVED |
Outstanding Inspections
Permit Status: Issued
Permit Number: TD-DEV-0423-00208
Permite Description: New building with parking and landscaping improvements
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/09/2026 | For trash and recycling enclosures | N/A | Partial Pass | 01/09/26 Wall built to 6' -Reinforcement correct. At end of walls and columns contractor is grouting embed plates from footer to top, just in the first cells that plates are embedded. the rest of wall has 1st lift grouted already. Rebar here will be wet set all the way down. Weep holes punched at bottom of these cells and contractor will send pictures of grout coming out of weep holes for each Refuse Enclosure. OK to grout second lift and embed plates. Vibrate allreinforce cells. |
Completed Inspections
Permit Status: Issued
Permit Number: TD-DEV-0423-00208
Permit Description: New building with parking and landscaping improvements
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/21/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | inform the contractor to call Ian inspection for SWPPP every two weeks. Contractor has installed the track out rocks and the wattles | |
| 01/12/2026 | Passed | 01/16/25 Benchmarks are marked on fence post for each site at Camino de Café. Each address was surveyed and rough graded to survey and plan. Parking area and PAAL are rough cut grade hubs were placed for grading but PAAL and parking area will be rolled and finished before density testing and blue tops are placed on subgrade. Basins are not cut/complete yet from each building down to Camino Café and then in the front along Camino Café. patients can be checked at intermediate or gading final final. |
||
| 02/19/2026 | Passed | |||
| 04/07/2026 | ENGR Paving | Passed | ||
| 04/07/2026 | Passed | |||
| 04/13/2026 | COT - ENGR - Signage Final | Passed | ||
| 04/13/2026 | For trash and recycling enclosures | Passed | ||
| 05/12/2026 | PDSD Site/Engineering Division - Landscaping | Passed | ||
| 05/12/2026 | ENGR - Drainage Structures | Passed | Riprap inlets at curb cuts all in place correct and drainage basins/channels look good. | |
| 05/20/2026 | ENGR Engineering Final | Passed |