Permit Details

Status:
Inspections
Type:
Development Package
Address:
8755 S RITA RD
Address NEW:
8755 S RITA RD
Apply Date:
03/25/2026
Applicant:
Charlie Smith
Description:
This Development Package submittal is a follow-up to the previous Development Package submitted under Plan Number TP-PRE-1125-00238 for the proposed wastewater pretreatment facility expansion at the Faribault Foods, Inc (Arizona Canning Company, LLC) site. This separate Development Package is associated with "At-risk Grading" in relation to the previous Development Package application and proposes to include only site grading work and proposed below grade wastewater piping associated with the project to improve the overall project timeline.

Permit Reviews

Permit Number - TD-DEV-0326-00077
Permit Status: Inspections
Permit Description: This Development Package submittal is a follow-up to the previous Development Package submitted under Plan Number TP-PRE-1125-00238 for the proposed wastewater pretreatment facility expansion at the Faribault Foods, Inc (Arizona Canning Company, LLC) site. This separate Development Package is associated with "At-risk Grading" in relation to the previous Development Package application and proposes to include only site grading work and proposed below grade wastewater piping associated with the project to improve the overall project timeline.
Start Date Submittal Complete Date Status  
03/27/2026 DEVELOPMENT PACKAGE NEW v.1 04/02/2026 APPROVED Review Details

Completed Inspections

Permit Status: Inspections
Permit Number: TD-DEV-0326-00077
Permit Description: This Development Package submittal is a follow-up to the previous Development Package submitted under Plan Number TP-PRE-1125-00238 for the proposed wastewater pretreatment facility expansion at the Faribault Foods, Inc (Arizona Canning Company, LLC) site. This separate Development Package is associated with "At-risk Grading" in relation to the previous Development Package application and proposes to include only site grading work and proposed below grade wastewater piping associated with the project to improve the overall project timeline.
Total Completed Inspections - 2
Date Description Inspector Results Comments
06/10/2026 PDSD Engineering Division Pre-Construction SITE Passed
07/07/2026 Passed Overex areas backfilled and compacted. Call in a flatwork inspection after reinforcing steel is installed.