Permit: TD-DEV-0326-00062
Permit Details
Status:
Inspections
Type:
Development Package
Address:
5001 S NOGALES HY
Address NEW:
5001 S NOGALES HY
Apply Date:
03/16/2026
Applicant:
Kappcon Inc. General Contractor
Description:
Linked to CIP-0824-00028-This project is for prop 407 improvements to Rudy Garcia Park. These improvements include walking path around entire park, upgrade sports lighting, renovate restrooms and basketball courts.
Permit Reviews
Permit Number - TD-DEV-0326-00062
Permit Status: Inspections
Permit Description: Linked to CIP-0824-00028-This project is for prop 407 improvements to Rudy Garcia Park. These improvements include walking path around entire park, upgrade sports lighting, renovate restrooms and basketball courts.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/16/2026 | DEVELOPMENT PACKAGE NEW v.1 | 03/23/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TD-DEV-0326-00062
Permit Status: Inspections
Permit Description: Linked to CIP-0824-00028-This project is for prop 407 improvements to Rudy Garcia Park. These improvements include walking path around entire park, upgrade sports lighting, renovate restrooms and basketball courts.
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/16/2026 | Prior to Final documents, fees and contractor |
Conditions
Permit Number - TD-DEV-0326-00062
Permit Status: Inspections
Permit Description: Linked to CIP-0824-00028-This project is for prop 407 improvements to Rudy Garcia Park. These improvements include walking path around entire park, upgrade sports lighting, renovate restrooms and basketball courts.
| Date | Description | Comments |
|---|---|---|
| 03/16/2026 | Dust Control/Air Quality Permit is Required. (Utilized with DP's & TP's) |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0326-00062
Permit Description: Linked to CIP-0824-00028-This project is for prop 407 improvements to Rudy Garcia Park. These improvements include walking path around entire park, upgrade sports lighting, renovate restrooms and basketball courts.
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/30/2026 | PDSD Engineering Division Pre-Construction SITE | Passed | NOI or NDC, SWPPP Book, Board And wattle will be in place for Storm Water Initial Inspection. Schedule this inspection when ready. Inspections needed for DP: Sidewalk/flatwork-schedule this for Curb ramps and reinforcing/dowels Site Consultation Striping Signage Engineering Final |
|
| 07/02/2026 | SITE - Stormwater Setup and Controls | Passed | BMP's in place per SWPPP plan. Non-discharge certificate and SWPPP book will be in trailer. Okay to start work. |