Permit: TD-DEV-0325-00083
Permit Details
Status:
Complete
Type:
Development Package
Address:
3429 E WILLARD ST
Address NEW:
3429 E WILLARD ST
Apply Date:
03/13/2025
Applicant:
Charles Pifer
Description:
CIP Related-Replace existing sidewalks, install security doors and site fencing. New ramada and bike garage. Associated with energov # CIP-0624-00019.
Permit Reviews
Permit Number - TD-DEV-0325-00083
Permit Status: Complete
Permit Description: CIP Related-Replace existing sidewalks, install security doors and site fencing. New ramada and bike garage. Associated with energov # CIP-0624-00019.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/18/2025 | DEVELOPMENT PACKAGE NEW v.2 | 05/06/2025 | APPROVED |
| 03/18/2025 | DEVELOPMENT PACKAGE NEW v.1 | 03/27/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TD-DEV-0325-00083
Permit Status: Complete
Permit Description: CIP Related-Replace existing sidewalks, install security doors and site fencing. New ramada and bike garage. Associated with energov # CIP-0624-00019.
| Date | Description | Comments |
|---|---|---|
| 03/18/2025 | Prior to Final documents, fees and contractor |
Outstanding Inspections
Permit Status: Complete
Permit Number: TD-DEV-0325-00083
Permite Description: CIP Related-Replace existing sidewalks, install security doors and site fencing. New ramada and bike garage. Associated with energov # CIP-0624-00019.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/10/2025 | Consultation SITE | N/A | Partial Pass | Site Consultation to discuss roof water discharge at entry points and accessible routes. Walked the site to understand the situation. Planning and Development will follow up with detailed requirements. |
| 11/05/2025 | N/A | Partial Pass | Contractors good to pour for the bollards in front south east corner |
Completed Inspections
Permit Status: Complete
Permit Number: TD-DEV-0325-00083
Permit Description: CIP Related-Replace existing sidewalks, install security doors and site fencing. New ramada and bike garage. Associated with energov # CIP-0624-00019.
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/01/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | contractors good to proceed with construction. this apartments are section 8 for the City Of Tucson | |
| 11/18/2025 | Passed | Sidewalks in front of both southern most units are formed correctly with appropriate slopes. Okay to pour. | ||
| 01/15/2026 | ENGR Engineering Final | Passed | All development package work is complete in accordance with approved plans. Site is safe to access. | |
| 01/15/2026 | LAND Landscape Appearance & Function Final | Passed | All landscape plants and materials are installed in accordance with approved plans. | |
| 01/15/2026 | Passed | Irrigation system is installed and functional in accordance with approved plans. | ||
| 01/15/2026 | Passed | All site handrails and bollards are complete. |