Permit Details

Status:
Complete
Type:
Development Package
Address:
3201 S PARK AV
Address NEW:
3201 S PARK AV
Apply Date:
01/25/2023
Applicant:
Description:
Development Package for a proposed Take 5 Oil Change facility located within Tucson Marketplace

Permit Reviews

Permit Number - TD-DEV-0123-00119
Permit Status: Complete
Permit Description: Development Package for a proposed Take 5 Oil Change facility located within Tucson Marketplace
Start Date Submittal Complete Date Status  
07/25/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/29/2025 APPROVED Review Details
12/01/2023 DEVELOPMENT PACKAGE NEW v.2 12/31/2023 APPROVED Review Details
01/26/2023 DEVELOPMENT PACKAGE REVIEW v.1 03/04/2023 REQUIRES RESUBMIT Review Details
04/20/2023 DEVELOPMENT PACKAGE REVIEW v.2 05/20/2023 REQUIRES RESUBMIT Review Details
09/18/2023 DEVELOPMENT PACKAGE NEW v.1 10/24/2023 REQUIRES RESUBMIT Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: TD-DEV-0123-00119
Permite Description: Development Package for a proposed Take 5 Oil Change facility located within Tucson Marketplace
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
02/25/2025 SITE - Sign Footer/Setback/Excavation Layout/Rebar N/A Not Ready Slab pitch wrong, side to side more than 3” must pitch to front 1.5%
07/17/2025 ENGR Grading Final N/A Partial Pass Sidewalks on the south side are good.
Sidewalks on the west side need rails as we are over the 5% margin coming into 7%+ on numbers.
All other sidewalks look good.

Verified slopes, see notes on sidewalks

Monuments (blue top) were not seen on grade for asphalt areas.
07/17/2025 ENGR Paving N/A Partial Pass Monuments (blue top) were not seen on grade for asphalt areas.
07/25/2025 N/A Partial Pass Scupper and Flatwork all look good. handrails are installed and correct. Third party compaction test results/proctors need to be submitted to the permit for final
07/25/2025 N/A Partial Pass Both Handrails at ramps providing Access to S Park are correct.

Completed Inspections

Permit Status: Complete
Permit Number: TD-DEV-0123-00119
Permit Description: Development Package for a proposed Take 5 Oil Change facility located within Tucson Marketplace
Total Completed Inspections - 6
Date Description Inspector Results Comments
12/04/2024 PDSD Engineering Division Pre-Construction SITE Passed Pre Con was completed after job was started.

Pate Supers (12/03/2024): Field contact name : Jason Schoneck, phone number: (520) 405-5760.
Please call half hour prior to inspection. Thank you.
03/11/2025 For trash and recycling enclosures Passed Note: slab is being poured with a 4" side to side pitch. I've asked for clarification on this and engineer has said it is correct.
07/17/2025 Passed
08/08/2025 COT - ENGR - Signage Final Passed All signs permitted have been installed. Sign company needs to call in the sign electrical final.
08/14/2025 ENGR Engineering Final Passed Issues with the hill being stabilized to the east has been corrected.
08/18/2025 LAND Landscape Appearance & Function Final Passed All Items have been corrected

Documents

File Name Document Type  
4_DRAINAGE RPT_V2.PDF DOCUMENTS VIEW
APPROVED DEVELOPMENT LETTER-MERGE.PDF DOCUMENTS VIEW
TEP FACILITIES MAP.PDF DOCUMENTS VIEW
APPROVED 4_DEVELOPMENT PACKAGE_V4.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
2_DEVELOPMENT PACKAGE_V2.PDF DOCUMENTS VIEW
1_DEVELOPMENT PACKAGE_V1.PDF DOCUMENTS VIEW
1_DRAINAGE STATEMENT_V1.PDF DOCUMENTS VIEW
1_GEOTECH RPT_V1.PDF DOCUMENTS VIEW