Permit: TC-SOL-0725-00989
Permit Details
Apply Date:
07/21/2025
Applicant:
Clay Mauldin
Description:
REV. 1: 09/17/2025 PV Roof Mounted System
Permit Reviews
Permit Number - TC-SOL-0725-00989
Permit Status: Complete
Permit Description: REV. 1: 09/17/2025
PV Roof Mounted System
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/17/2025 | RESIDENTIAL SOLAR REVISION v.1 | 09/17/2025 | APPROVED |
| 07/21/2025 | RESIDENTIAL SOLAR APP v.1 | 07/21/2025 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-SOL-0725-00989
Permite Description: REV. 1: 09/17/2025
PV Roof Mounted System
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/11/2025 | BULD - Electrical Clearance | N/A | Partial Pass | Partial fr the 80A meter adapter - DGL Clearance was called into TEP at 11:30 am Pending solar final |
| 09/18/2025 | COT - RSOL - Electrical Final Solar Project | N/A | Re-inspection required | 9/18/25 Missing pictures of Main panel dead front, we need to see backfeed breaker location and labels on the inside. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-0725-00989
Permit Description: REV. 1: 09/17/2025
PV Roof Mounted System
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/18/2025 | BULD - Electrical Clearance | Passed | 9/18/25 TEP CLEARANCE: DGC |
|
| 09/18/2025 | COT - RSOL - Electrical Final Solar Project | Passed |