Permit: TC-SOL-0525-00599
Permit Details
Apply Date:
05/06/2025
Applicant:
Hailey McGraw
Description:
REV B: The main service panel rating has been revised, as reflected on PV-4 REV A: The main service panel rating has been revised 4.05 kW DC System- Roof Mount PV w/ storage ,MPU 200/200, existing system
Permit Reviews
Permit Number - TC-SOL-0525-00599
Permit Status: Inspections
Permit Description: REV B: The main service panel rating has been revised, as reflected on PV-4
REV A: The main service panel rating has been revised
4.05 kW DC System- Roof Mount PV w/ storage ,MPU 200/200, existing system
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/17/2025 | RESIDENTIAL SOLAR REVISION v.1 | 06/17/2025 | APPROVED |
| 06/02/2025 | RESIDENTIAL SOLAR REVISION v.1 | 06/02/2025 | APPROVED |
| 05/06/2025 | RESIDENTIAL SOLAR APP v.1 | 05/06/2025 | APPROVED |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-SOL-0525-00599
Permite Description: REV B: The main service panel rating has been revised, as reflected on PV-4
REV A: The main service panel rating has been revised
4.05 kW DC System- Roof Mount PV w/ storage ,MPU 200/200, existing system
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/01/2025 | BULD - Electrical Clearance | N/A | Partial Pass | Partial for the Tesla switch - DGL Clearance was called into TEP at 11:00 am Pending solar final (new panel has a 175A derate) |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-SOL-0525-00599
Permit Description: REV B: The main service panel rating has been revised, as reflected on PV-4
REV A: The main service panel rating has been revised
4.05 kW DC System- Roof Mount PV w/ storage ,MPU 200/200, existing system
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/03/2025 | BULD - Electrical Clearance | Passed | 11.3.25 APPROVED DGC/BAT |
|
| 11/03/2025 | COT - RSOL - Electrical Final Solar Project | Passed | 11.3.25 APPROVED DGC/BAT |