Inspection History Details
Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/18/2025 | BULD - Electrical Clearance | Partial Pass | TEP CLEARANCE: INCR, called TEP @ 12:05. Partial pass pending solar. | |
| 10/01/2025 | BULD - Electrical Clearance | Partial Pass | Partial for the Tesla switch - DGL Clearance was called into TEP at 11:00 am Pending solar final (new panel has a 175A derate) |
|
| 11/03/2025 | BULD - Electrical Clearance | Passed | 11.3.25 APPROVED DGC/BAT |