Permit: TC-SOL-0425-00561
Permit Details
Apply Date:
04/29/2025
Applicant:
Project Manager
Description:
REV 1: Install Pics Installation of a 8.715kw dc system/1 Battery/MPU 225A
Permit Reviews
Permit Number - TC-SOL-0425-00561
Permit Status: Complete
Permit Description: REV 1: Install Pics
Installation of a 8.715kw dc system/1 Battery/MPU 225A
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/29/2025 | RESIDENTIAL SOLAR APP v.1 | 04/29/2025 | APPROVED |
| 07/10/2025 | RESIDENTIAL SOLAR REVISION v.1 | 07/10/2025 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-SOL-0425-00561
Permite Description: REV 1: Install Pics
Installation of a 8.715kw dc system/1 Battery/MPU 225A
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/04/2025 | BULD - Electrical Clearance | N/A | Partial Pass | Partial for the 200A service panel upgrade - INCR Clearance to TEP is required for the cutover - pending solar |
| COT - RSOL - Electrical Final Solar Project | N/A | Not Ready | 6/4/25 - Partial for the 200A service panel upgrade - INCR Clearance to TEP is required for the cutover - pending solar |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-0425-00561
Permit Description: REV 1: Install Pics
Installation of a 8.715kw dc system/1 Battery/MPU 225A
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/11/2025 | BULD - Electrical Clearance | Passed | Approved with pics - DGC/BAT Clearance to TEP is required for the solar meter | |
| 07/11/2025 | COT - RSOL - Electrical Final Solar Project | Passed |