Permit: TC-SOL-0425-00450
Permit Details
Apply Date:
04/08/2025
Applicant:
Project Manager
Description:
REV 1: Install Pics Installation of a 4.150kw dc system/1 Battery
Permit Reviews
Permit Number - TC-SOL-0425-00450
Permit Status: Complete
Permit Description: REV 1: Install Pics
Installation of a 4.150kw dc system/1 Battery
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/09/2025 | RESIDENTIAL SOLAR APP v.1 | 04/09/2025 | APPROVED |
| 06/03/2025 | RESIDENTIAL SOLAR REVISION v.1 | 06/03/2025 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-SOL-0425-00450
Permit Description: REV 1: Install Pics
Installation of a 4.150kw dc system/1 Battery
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/04/2025 | BULD - Electrical Clearance | Passed | Approved solar with powerwall-3 per pics - DGC/BAT Clearance to TEP is required for the solar meter | |
| 06/04/2025 | COT - RSOL - Electrical Final Solar Project | Passed | Approved solar with powerwall-3 per pics - DGC/BAT Clearance to TEP is required for the solar meter |