Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Inspections
Type:
Solar
Address NEW:
2211 S CAMINO SECO
Apply Date:
03/20/2026
Applicant:
Juana Quiroz
Description:
Rooftop Mounted Solar Energy System PV+ST 22 SIL-410QD solar modules 1 SE7600H-US {240V} inverter 1 BAT-10K1P battery Main Panel Upgrade: Yes Derate: Yes System Size: 9.02 kW DC (7.6 kW AC)

Permit Reviews

Permit Number - TC-SOL-0326-00196
Permit Status: Inspections
Permit Description: Rooftop Mounted Solar Energy System PV+ST 22 SIL-410QD solar modules 1 SE7600H-US {240V} inverter 1 BAT-10K1P battery Main Panel Upgrade: Yes Derate: Yes System Size: 9.02 kW DC (7.6 kW AC)
Start Date Submittal Complete Date Status  
03/20/2026 RESIDENTIAL SOLAR APP v.1 N/A APPROVED Review Details

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-SOL-0326-00196
Permite Description: Rooftop Mounted Solar Energy System PV+ST 22 SIL-410QD solar modules 1 SE7600H-US {240V} inverter 1 BAT-10K1P battery Main Panel Upgrade: Yes Derate: Yes System Size: 9.02 kW DC (7.6 kW AC)
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
05/21/2026 BULD - Electrical Clearance N/A Re-inspection required 05/21/2026
Approved plans call for 100A main breaker. Currently installed in field is 125A breaker.
05/21/2026 COT - RSOL - Electrical Final Solar Project N/A Re-inspection required 05/21/2026
Approved plans call for 100A main breaker. Currently installed in field is 125A breaker.

Completed Inspections

Permit Status: Inspections
Permit Number: TC-SOL-0326-00196
Permit Description: Rooftop Mounted Solar Energy System PV+ST 22 SIL-410QD solar modules 1 SE7600H-US {240V} inverter 1 BAT-10K1P battery Main Panel Upgrade: Yes Derate: Yes System Size: 9.02 kW DC (7.6 kW AC)
Total Completed Inspections - 2
Date Description Inspector Results Comments
05/21/2026 BULD - Electrical Clearance Passed 05/21/2026
Approved clearance TEP DGC/BAT. Verified correction to prior inspection.
05/21/2026 COT - RSOL - Electrical Final Solar Project Passed 05/21/2026
Approved clearance TEP DGC/BAT. Verified correction to prior inspection.

Documents

File Name Document Type  
APPROVAL-DOCUMENT-SA20260320-9-178-4495-A_V1.PDF DOCUMENTS VIEW
APPROVAL-UPLOADS-SA20260320-9-178-4495-A_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
CONS-IND-5567RONALD FURTAKPLANSV003-19-2026_V1.PDF DOCUMENTS VIEW