Inspection History Details
Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/13/2026 | BULD - Electrical Clearance | Partial Pass | 5/13/26 TEP CLEARANCE: INCR, called in at 11:07. Partial pass |
|
| 05/21/2026 | BULD - Electrical Clearance | Passed | 05/21/2026 Approved clearance TEP DGC/BAT. Verified correction to prior inspection. |
|
| 05/21/2026 | BULD - Electrical Clearance | Re-inspection required | 05/21/2026 Approved plans call for 100A main breaker. Currently installed in field is 125A breaker. |