Permit: TC-RES-1224-07361
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
9579 E HARKES DR
Address NEW:
9579 E HARKES DR
Apply Date:
12/18/2024
Applicant:
Natalia Soto
Description:
9.085KW Roof Mounted PV Installation 23 Modules
Permit Reviews
Permit Number - TC-RES-1224-07361
Permit Status: Complete
Permit Description: 9.085KW Roof Mounted PV Installation 23 Modules
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/30/2025 | RESIDENTIAL SOLAR REVISION v.1 | 06/17/2025 | APPROVED |
| 12/19/2024 | RESIDENTIAL SOLAR v.1 | 01/21/2025 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-1224-07361
Permite Description: 9.085KW Roof Mounted PV Installation 23 Modules
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/26/2025 | RSBU - Building Final | N/A | Partial Pass | 6.26.26 PV system is installed according to plan. Proper sized conductors verified. Bonding and grounding verified. White neutrals verified. Proper amperage and breaker sizes verified. All labels verified EXCEPT equipment placard at main panel. PARTIAL PASS PENDING PHOTO PF PLACARD. |
| 06/26/2025 | COT - RSOL - Electrical Final Solar Project | N/A | Partial Pass | 6.26.26 PV system is installed according to plan. Proper sized conductors verified. Bonding and grounding verified. White neutrals verified. Proper amperage and breaker sizes verified. All labels verified EXCEPT equipment placard at main panel. PARTIAL PASS PENDING PHOTO PF PLACARD. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-1224-07361
Permit Description: 9.085KW Roof Mounted PV Installation 23 Modules
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/22/2025 | RSBU - Building Final | Passed | 7/22/25 corrections made CLEARANCE DGC | |
| 07/22/2025 | COT - RSOL - Electrical Final Solar Project | Passed | 7/22/25 corrections made CLEARANCE DGC | |
| 07/22/2025 | BULD - Electrical Clearance | Passed | 7/22/25 corrections made CLEARANCE DGC |