Permit: TC-RES-1224-07301
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
818 W CALLE ANTONIA
Address NEW:
818 W CALLE ANTONIA
Apply Date:
12/16/2024
Applicant:
Hailey McGaw
Description:
ROOF MOUNTED PHOTOVOLTAIC SYSTEM - 7.29 KW (DC), 5.85 KW (AC) (18) NEW RUNERGY; HY_DH108P8B_405 - 405W MODULES (18) NEW MICRO-INVERTERS; ENPHASE; IQ8M-72-2-US (1) NEW PV AC COMBINER PANEL WITH ENPHASE ENVOY MONITORING SYSTEM (1) NEW UTILITY DG DISCONNECT (1) NEW DG METER (1) NEW METER SOCKET ADAPTER INTERCONNECTION (1) NEW METER SOCKET RELOCATED NEW PHOTOVOLTAIC ROOF MOUNTING HARDWARE NEW INTEGRATED GROUND BONDING HARDWARE
Permit Reviews
Permit Number - TC-RES-1224-07301
Permit Status: Complete
Permit Description: ROOF MOUNTED PHOTOVOLTAIC SYSTEM - 7.29 KW (DC), 5.85 KW (AC)
(18) NEW RUNERGY; HY_DH108P8B_405 - 405W MODULES
(18) NEW MICRO-INVERTERS; ENPHASE; IQ8M-72-2-US
(1) NEW PV AC COMBINER PANEL WITH ENPHASE ENVOY
MONITORING SYSTEM
(1) NEW UTILITY DG DISCONNECT
(1) NEW DG METER
(1) NEW METER SOCKET ADAPTER INTERCONNECTION
(1) NEW METER SOCKET RELOCATED
NEW PHOTOVOLTAIC ROOF MOUNTING HARDWARE
NEW INTEGRATED GROUND BONDING HARDWARE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/17/2024 | RESIDENTIAL SOLAR v.1 | 01/17/2025 | APPROVED |
| 04/25/2025 | RESIDENTIAL SOLAR REVISION v.1 | 05/28/2025 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-1224-07301
Permit Description: ROOF MOUNTED PHOTOVOLTAIC SYSTEM - 7.29 KW (DC), 5.85 KW (AC)
(18) NEW RUNERGY; HY_DH108P8B_405 - 405W MODULES
(18) NEW MICRO-INVERTERS; ENPHASE; IQ8M-72-2-US
(1) NEW PV AC COMBINER PANEL WITH ENPHASE ENVOY
MONITORING SYSTEM
(1) NEW UTILITY DG DISCONNECT
(1) NEW DG METER
(1) NEW METER SOCKET ADAPTER INTERCONNECTION
(1) NEW METER SOCKET RELOCATED
NEW PHOTOVOLTAIC ROOF MOUNTING HARDWARE
NEW INTEGRATED GROUND BONDING HARDWARE
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/13/2025 | RSBU - Building Final | Passed | passed final 3/13/25 CLEARANCE DGC | |
| 06/04/2025 | BULD - Electrical Clearance | Passed | Approved solar - DGC Clearance to TEP is required for the solar meter | |
| 06/04/2025 | COT - RSOL - Grounding/Bonding Solar Project | Passed | ||
| 06/04/2025 | COT - RSOL - Electrical Final Solar Project | Passed | Approved solar - DGC Clearance to TEP is required for the solar meter |