Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address NEW:
818 W CALLE ANTONIA
Apply Date:
12/16/2024
Applicant:
Hailey McGaw
Description:
ROOF MOUNTED PHOTOVOLTAIC SYSTEM - 7.29 KW (DC), 5.85 KW (AC) (18) NEW RUNERGY; HY_DH108P8B_405 - 405W MODULES (18) NEW MICRO-INVERTERS; ENPHASE; IQ8M-72-2-US (1) NEW PV AC COMBINER PANEL WITH ENPHASE ENVOY MONITORING SYSTEM (1) NEW UTILITY DG DISCONNECT (1) NEW DG METER (1) NEW METER SOCKET ADAPTER INTERCONNECTION (1) NEW METER SOCKET RELOCATED NEW PHOTOVOLTAIC ROOF MOUNTING HARDWARE NEW INTEGRATED GROUND BONDING HARDWARE

Permit Reviews

Permit Number - TC-RES-1224-07301
Permit Status: Complete
Permit Description: ROOF MOUNTED PHOTOVOLTAIC SYSTEM - 7.29 KW (DC), 5.85 KW (AC) (18) NEW RUNERGY; HY_DH108P8B_405 - 405W MODULES (18) NEW MICRO-INVERTERS; ENPHASE; IQ8M-72-2-US (1) NEW PV AC COMBINER PANEL WITH ENPHASE ENVOY MONITORING SYSTEM (1) NEW UTILITY DG DISCONNECT (1) NEW DG METER (1) NEW METER SOCKET ADAPTER INTERCONNECTION (1) NEW METER SOCKET RELOCATED NEW PHOTOVOLTAIC ROOF MOUNTING HARDWARE NEW INTEGRATED GROUND BONDING HARDWARE
Start Date Submittal Complete Date Status  
12/17/2024 RESIDENTIAL SOLAR v.1 01/17/2025 APPROVED Review Details
04/25/2025 RESIDENTIAL SOLAR REVISION v.1 05/28/2025 APPROVED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-1224-07301
Permit Description: ROOF MOUNTED PHOTOVOLTAIC SYSTEM - 7.29 KW (DC), 5.85 KW (AC) (18) NEW RUNERGY; HY_DH108P8B_405 - 405W MODULES (18) NEW MICRO-INVERTERS; ENPHASE; IQ8M-72-2-US (1) NEW PV AC COMBINER PANEL WITH ENPHASE ENVOY MONITORING SYSTEM (1) NEW UTILITY DG DISCONNECT (1) NEW DG METER (1) NEW METER SOCKET ADAPTER INTERCONNECTION (1) NEW METER SOCKET RELOCATED NEW PHOTOVOLTAIC ROOF MOUNTING HARDWARE NEW INTEGRATED GROUND BONDING HARDWARE
Total Completed Inspections - 4
Date Description Inspector Results Comments
03/13/2025 RSBU - Building Final Passed passed final 3/13/25 CLEARANCE DGC
06/04/2025 BULD - Electrical Clearance Passed Approved solar - DGC Clearance to TEP is required for the solar meter
06/04/2025 COT - RSOL - Grounding/Bonding Solar Project Passed
06/04/2025 COT - RSOL - Electrical Final Solar Project Passed Approved solar - DGC Clearance to TEP is required for the solar meter

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
AZ-R24102_TRILLO, TILLY_PLANS V3_V1.PDF DOCUMENTS VIEW
AZ-R24102_TRILLO, TILLY_REVISION LETTER_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-AZ-R24102_TRILLO, TILLY_PLANS V2_V1.PDF DOCUMENTS VIEW