Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-RES-1223-10006
Permit Details
Status:
Inspections
Type:
Residential Building - One or Two Family
Address:
3938 E ELMWOOD ST
Address NEW:
3938 E ELMWOOD ST
Apply Date:
12/11/2023
Applicant:
hector gomez
Description:
SFR Lot 2
Permit Reviews
Permit Number - TC-RES-1223-10006
Permit Status: Inspections
Permit Description: SFR Lot 2
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/28/2024 | RESIDENTIAL NEW DWELLING v.5 | 07/31/2024 | REQUIRES RESUBMIT |
| 12/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/23/2024 | APPROVED |
| 10/23/2024 | RESIDENTIAL NEW DWELLING v.1 | 10/23/2024 | APPROVED |
| 12/13/2023 | RESIDENTIAL NEW DWELLING v.1 | 01/02/2024 | REQUIRES RESUBMIT |
| 08/22/2024 | RESTAMP - RESIDENTIAL v.1 | 08/22/2024 | REQUIRES RESUBMIT |
| 01/12/2024 | RESIDENTIAL NEW DWELLING v.3 | 01/25/2024 | REQUIRES RESUBMIT |
| 02/13/2024 | RESIDENTIAL NEW DWELLING v.4 | 04/09/2024 | REQUIRES RESUBMIT |
| 01/10/2024 | RESIDENTIAL NEW DWELLING v.2 | 01/10/2024 | REQUIRES RESUBMIT |
| 08/23/2024 | RESIDENTIAL NEW DWELLING v.1 | 08/28/2024 | APPROVED |
| 10/21/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/23/2024 | APPROVED |
| 08/15/2024 | RESIDENTIAL NEW DWELLING v.6 | 08/22/2024 | APPROVED |
Conditions
Permit Number - TC-RES-1223-10006
Permit Status: Inspections
Permit Description: SFR Lot 2
| Date | Description | Comments |
|---|---|---|
| 12/27/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 12/27/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-RES-1223-10006
Permite Description: SFR Lot 2
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/28/2024 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Not Ready | Will reschedule when rebar is in place. |
| 05/06/2025 | COT - RSEL - Outdoor Lighting | N/A | Partial Pass | rough in |
| 05/06/2025 | COT - RSPL - Gas Pressure Test | N/A | Not Applicable | |
| 10/28/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | Will reschedule when intermediates are ready. |
| 06/26/2025 | COT - RSBU - Interior Shear Bracing | N/A | Not Applicable | |
| 06/02/2025 | COT - RSPL - Sewer | N/A | Partial Pass | Partial pass. Sewer lines to second clean outs approved. Okay to backfill progress areas. Shading required. Pending tie into main sewer line. 6/2/2025 |
| 10/22/2025 | COT - BULD - SWG Clearance | N/A | Not Ready | unable to access unit |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-RES-1223-10006
Permit Description: SFR Lot 2
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/01/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Ok to place concrete (mono-pour) in slab area. Electric ufer is placed in Northwest corner of footings. | |
| 11/01/2024 | COT - RSBU - Preslab | Passed | Ensure slab area is properly termite treated. | |
| 11/27/2024 | COT - RSBU - Masonry Pregrout | Passed | Final lift for both interior and west wall approved. Okay to fully grout. 11/27/2024 | |
| 12/02/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 05/06/2025 | COT - RSEL - Electrical Underground | Passed | ||
| 05/06/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 05/06/2025 | COT - RSPL - Rough Soil | Passed | ||
| 06/02/2025 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading required. 6/2/2025 | |
| 06/26/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 06/26/2025 | COT - RSEL - Grounding/Bonding | Passed | ||
| 06/26/2025 | COT - RSPL - Sewer | Passed | ||
| 09/18/2025 | BULD - Electrical Clearance | Passed | TEP CLEARANCE: ECO |