Permit: TC-RES-1125-05611
Permit Details
Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address:
1656 S SAN ANTONIO DR UNIT 1
Address NEW:
1656 S SAN ANTONIO DR UNIT 1
Apply Date:
11/19/2025
Applicant:
Ana Rojas
Description:
Duplex
Permit Reviews
Permit Number - TC-RES-1125-05611
Permit Status: Inspections complete
Permit Description: Duplex
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/25/2025 | RESIDENTIAL NEW DWELLING v.1 | 12/05/2025 | REQUIRES RESUBMIT |
| 04/15/2026 | RESIDENTIAL NEW DWELLING v.2 | 05/01/2026 | APPROVED |
| 05/06/2026 | ADMINISTRATIVE v.2 | N/A | REQUIRES RESUBMIT |
| 05/01/2026 | ADMINISTRATIVE v.1 | N/A | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-RES-1125-05611
Permit Status: Inspections complete
Permit Description: Duplex
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 11/26/2025 | Submit the Air Leakage & Duct Tightness Test Report completed by an Approved Special Inspector prior to Final Inspections. |
| 11/26/2025 | Manual J report |
| 11/26/2025 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Conditions
Permit Number - TC-RES-1125-05611
Permit Status: Inspections complete
Permit Description: Duplex
| Date | Description | Comments |
|---|---|---|
| 11/25/2025 | The permit and plan show to be for a Duplex and requires two separate addresses, one for each unit of the duplex. Please contact Pima County Addressing at addressing@pima.gov or 520-724-9512 to assign/add the units or a new address for this Duplex. A change of address request will need to be submitted in order to properly update the location of this permit once the addressing is complete. Instructions can be found here to request change of address: https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/sub-records.pdf For questions: PDSD-Residential@tucsonaz.gov | |
| 11/25/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 11/25/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-1125-05611
Permite Description: Duplex
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/26/2026 | COT - RSBU - Preslab | N/A | Re-inspection required | 5-26-26: clear out footings of loose debris, compact pad near interior footing, add reinforcement at hold-downs and extend reinforcement 2' at all corners, per IRC 506.3.3, a vapor retarder is required at all monolithic slabs & footings, 2 ground rods will be required rather than attaching copper to reinforcement, 1 1/2" clearance from DWV and forms. Note: an exception to the vapor barrier requires a stamped letter from an engineer. The letter would have to be submitted to the city for review and approval. |
| 06/17/2026 | COT - RSBU - Firewall/Fire Barrier/Firestop | N/A | Partial Pass | 06/17/2026 Verified 5/8" type-x gypsum at interior common firewall. Partial pass pending exterior panels, call in prior to tape and texture. |
| 10/05/2026 | RSBU - Building Final | N/A | Re-inspection required | 10/5/26: reverse polarity at southwest receptacle of bedroom 3, add insulation to hot leg of water heaters, and relocate pex lines at entrance to attic. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-1125-05611
Permit Description: Duplex
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/19/2026 | COT - RSPL - Rough Soil | Passed | Okay to backfill. Shading required. 5/19/2026 | |
| 05/29/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 05/29/2026 | COT - RSBU - Preslab | Passed | 5/29/2026 all corrections were made. Okay for concrete placement. | |
| 06/18/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 06/18/2026 Verified added short pins at marked locations and tightened anchor bolts throughout. |
|
| 07/08/2026 | COT - RSPL - Yard Water Line | Passed | Okay to backfill. Shading required. 7/8/2026 | |
| 07/10/2026 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. UNITS 1 AND 2. 7/10/2026 | |
| 07/10/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | All corrections have been made. 7/10/2026 | |
| 07/21/2026 | COT - RSBU - Interior Shear Bracing | Passed | ||
| 07/21/2026 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | 07/21/2026 Verified nail schedule at firewall. |
|
| 07/27/2026 | COT - RSBU - Roof Nailing | Passed | 07/27/2026 Passed prior on 6/18/26. |
|
| 09/08/2026 | COT - RSPL - Sewer | Passed | 9/8/26: sewer verified under test & approved. Okay to backfill using shading materials. | |
| 10/05/2026 | COT - RSEL - Electrical Underground | Passed | 10/5/26: approved. | |
| 10/05/2026 | COT - RSEL - Outdoor Lighting | Passed | 10/5/26: approved. | |
| 10/05/2026 | COT - RSME - Mechanical Final | Passed | 10/5/26: mechanical final approved. | |
| 10/05/2026 | COT - RSPL - Plumbing Final | Passed | 10/5/26: plumbing final approved. | |
| 10/06/2026 | RSBU - Building Final | Passed | 10/6/26: building final approved. | |
| 10/06/2026 | COT - RSEL - Electrical Final | Passed | 10/6/26: electrical final approved. |