Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
In Review
Type:
Residential Building - One or Two Family
Address:
8551 E 23RD ST
Address NEW:
8551 E 23RD ST
Apply Date:
10/30/2026
Applicant:
Jared Behmer
Description:
We tore off an elastomeric foam roof down to roof deck on left side of existing roof only. . Aprox. 41x38 or 1558 square ft. Replaced 15 sheets of bad 1/2 inch sheathing with new 1/2 inch sheathing. Then installed an APOC Weather Armor FT-3 fleece top underlayment over the existing roof deck. Then installed a Polyiso tapered insulation board with 1/2 inch OSB on top of the insulation board. The taper system went from 1.5 inch to 4 1/8 inch, slope. Attached it with 3 inch insulation plates and screws. Then installed a Polyglass Elastoflex SA-V base underlayment over the 1/2 inch sheathing. Then installed a Polyglass SA-P granulated cap sheet over the base underlayment.

Permit Reviews

Permit Number - TC-RES-1026-06065
Permit Status: In review
Permit Description: We tore off an elastomeric foam roof down to roof deck on left side of existing roof only. . Aprox. 41x38 or 1558 square ft. Replaced 15 sheets of bad 1/2 inch sheathing with new 1/2 inch sheathing. Then installed an APOC Weather Armor FT-3 fleece top underlayment over the existing roof deck. Then installed a Polyiso tapered insulation board with 1/2 inch OSB on top of the insulation board. The taper system went from 1.5 inch to 4 1/8 inch, slope. Attached it with 3 inch insulation plates and screws. Then installed a Polyglass Elastoflex SA-V base underlayment over the 1/2 inch sheathing. Then installed a Polyglass SA-P granulated cap sheet over the base underlayment.
Start Date Submittal Complete Date Status  
11/04/2026 RESIDENTIAL ADD/ALT v.1 11/09/2026 APPROVED Review Details

Conditions

Permit Number - TC-RES-1026-06065
Permit Status: In review
Permit Description: We tore off an elastomeric foam roof down to roof deck on left side of existing roof only. . Aprox. 41x38 or 1558 square ft. Replaced 15 sheets of bad 1/2 inch sheathing with new 1/2 inch sheathing. Then installed an APOC Weather Armor FT-3 fleece top underlayment over the existing roof deck. Then installed a Polyiso tapered insulation board with 1/2 inch OSB on top of the insulation board. The taper system went from 1.5 inch to 4 1/8 inch, slope. Attached it with 3 inch insulation plates and screws. Then installed a Polyglass Elastoflex SA-V base underlayment over the 1/2 inch sheathing. Then installed a Polyglass SA-P granulated cap sheet over the base underlayment.
Date Description Comments
11/09/2026 Pre-Issuance - Required Documents - Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.

Outstanding Inspections

Permit Status: In Review
Permit Number: TC-RES-1026-06065
Permite Description: We tore off an elastomeric foam roof down to roof deck on left side of existing roof only. . Aprox. 41x38 or 1558 square ft. Replaced 15 sheets of bad 1/2 inch sheathing with new 1/2 inch sheathing. Then installed an APOC Weather Armor FT-3 fleece top underlayment over the existing roof deck. Then installed a Polyiso tapered insulation board with 1/2 inch OSB on top of the insulation board. The taper system went from 1.5 inch to 4 1/8 inch, slope. Attached it with 3 inch insulation plates and screws. Then installed a Polyglass Elastoflex SA-V base underlayment over the 1/2 inch sheathing. Then installed a Polyglass SA-P granulated cap sheet over the base underlayment.
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
11/16/2026 RSBU - Building Final N/A Re-inspection required 11/16/2026
Roof covered over prior to inspection. Provide verifiable evidence, such as detailed images or receipts, of full scope of work completed according to approved plan. Detailed images of roof decking for nail or fastener schedule suffices. The last rafter on the fascia shows evidence of rot, please provide evidence or open up part of rafter system covered over to ensure it is structurally sound.
11/16/2026 COT - RSBU - Roof Nailing N/A Re-inspection required 11/16/2026
Roof covered over prior to inspection. Provide verifiable evidence, such as detailed images or receipts, of full scope of work completed according to approved plan. Detailed images of roof decking for nail or fastener schedule suffices. The last rafter on the fascia shows evidence of rot, please provide evidence or open up part of rafter system covered over to ensure it is structurally sound.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
AERIAL VIEW PDF_V1.PDF DOCUMENTS VIEW
CONS-SCOPE OF WORK-8551-23RD-ST_V1.PDF DOCUMENTS VIEW
PLYWOOD REPLACEMENT PICTURE PDF_V1.PDF DOCUMENTS VIEW