Permit: TC-RES-1023-08500
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
926 W MACARTHUR ST
Address NEW:
926 W MACARTHUR ST
Apply Date:
10/03/2023
Applicant:
Bailey Randall
Description:
Roof Mounted PV System DC SYSTEM SIZE (kW): 9.6 kW / AC SYSTEM SIZE (kW): 6.96 kW With Main service panel upgrade 24 modules
Permit Reviews
Permit Number - TC-RES-1023-08500
Permit Status: Complete
Permit Description: Roof Mounted PV System DC SYSTEM SIZE (kW): 9.6 kW / AC SYSTEM SIZE (kW): 6.96 kW With Main service panel upgrade
24 modules
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/22/2023 | RESIDENTIAL SOLAR v.1 | 01/02/2024 | REQUIRES RESUBMIT |
| 09/09/2024 | RESIDENTIAL SOLAR REVISION v.1 | 09/10/2024 | REQUIRES RESUBMIT |
| 10/03/2023 | RESIDENTIAL SOLAR v.1 | 10/16/2023 | APPROVED |
| 09/17/2024 | RESIDENTIAL SOLAR REVISION v.2 | 09/27/2024 | APPROVED |
| 01/16/2024 | RESIDENTIAL SOLAR v.2 | 01/19/2024 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-1023-08500
Permite Description: Roof Mounted PV System DC SYSTEM SIZE (kW): 9.6 kW / AC SYSTEM SIZE (kW): 6.96 kW With Main service panel upgrade
24 modules
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/13/2023 | BULD - Electrical Clearance | N/A | Partial Pass | INCR ok for cutover future solar. |
| 11/14/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-1023-08500
Permit Description: Roof Mounted PV System DC SYSTEM SIZE (kW): 9.6 kW / AC SYSTEM SIZE (kW): 6.96 kW With Main service panel upgrade
24 modules
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/14/2024 | RSBU - Building Final | Passed | ||
| 11/14/2024 | COT - RSOL - Electrical Final Solar Project | Passed | ||
| 11/14/2024 | COT - RSOL - Grounding/Bonding Solar Project | Passed | ||
| 11/14/2024 | BULD - Electrical Clearance | Passed | Approved - DGC Clearance to TEP is required for the solar meter |