Inspection History Details
Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/06/2024 | BULD - Electrical Clearance | Partial Pass | Partial pass incr for cutover scheduling. | |
| 08/12/2024 | BULD - Electrical Clearance | Partial Pass | Partial cutover complete Pending solar and final - NR |
|
| 11/14/2024 | BULD - Electrical Clearance | Not Applicable | duplicate | |
| 11/14/2024 | BULD - Electrical Clearance | Passed | Approved - DGC Clearance to TEP is required for the solar meter | |
| 11/14/2024 | BULD - Electrical Clearance | Passed | Approved - DGC Clearance to TEP is required for the solar meter | |
| 12/13/2023 | BULD - Electrical Clearance | Partial Pass | INCR ok for cutover future solar. |