Permit: TC-RES-0924-05108
Permit Details
Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address:
9412 E 5TH ST
Address NEW:
9412 E 5TH ST
Apply Date:
09/05/2024
Applicant:
William Taylor
Description:
Rebuild SFR after fire
Permit Reviews
Permit Number - TC-RES-0924-05108
Permit Status: Inspections complete
Permit Description: Rebuild SFR after fire
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/05/2024 | RESIDENTIAL NEW DWELLING v.3 | 12/14/2024 | APPROVED |
| 10/28/2024 | RESIDENTIAL NEW DWELLING v.2 | 10/28/2024 | REQUIRES RESUBMIT |
| 09/19/2024 | RESIDENTIAL NEW DWELLING v.1 | 10/21/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-RES-0924-05108
Permit Status: Inspections complete
Permit Description: Rebuild SFR after fire
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 09/26/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
| 11/25/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0924-05108
Permit Description: Rebuild SFR after fire
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/27/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | 1/27/25: All items previously noted on the 1/15/25 inspection have been corrected and are complete. Okay to proceed with installation of insulation and drywall in ceilings and walls. | |
| 01/27/2025 | COT - RSBU - Roof Nailing | Passed | ||
| 01/27/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 1/27/25: Loose flex ductwork to a/c unit has been installed. Top plate around dryer vent has been fire foamed. Okay to proceed with installation of insulation and drywall on walls and ceilings. | |
| 01/27/2025 | COT - RSEL - Grounding/Bonding | Passed | 2 each ground rods are driven into the electrical trench 6' apart. Okay to backfill trench. | |
| 01/27/2025 | BULD - Electrical Clearance | Passed | 2 each ground rods are driven into the electrical trench 6' apart. Okay to backfill trench. | |
| 05/02/2025 | COT - RSPL - Plumbing Final | Passed | Passed final 5/2/25 | |
| 05/02/2025 | COT - RSME - Mechanical Final | Passed | Passed final 5/2/25 | |
| 05/02/2025 | RSBU - Building Final | Passed | Passed final 5/2/25 | |
| 05/02/2025 | COT - RSEL - Outdoor Lighting | Passed | Passed final 5/2/25 | |
| 05/02/2025 | COT - RSEL - Electrical Final | Passed | Passed final 5/2/25 |