Status:
Complete
Type:
Residential Building - One or Two Family
Apply Date:
09/20/2023
Applicant:
Sherilyn Soto
Description:
Installation of a new roof mounted 11.68 kw solar PV system. 32 modules

Permit Reviews

Permit Number - TC-RES-0923-08178
Permit Status: Complete
Permit Description: Installation of a new roof mounted 11.68 kw solar PV system. 32 modules
Start Date Submittal Complete Date Status  
09/20/2023 RESIDENTIAL SOLAR v.1 10/12/2023 APPROVED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-RES-0923-08178
Permite Description: Installation of a new roof mounted 11.68 kw solar PV system. 32 modules
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
11/30/2023 BULD - Electrical Clearance N/A Re-inspection required Called multiple times and left voicemails. Received a call back and was told it was the wrong number. Got to the site and gates were locked. Dogs are on site. Provide access to the site. 11/30/2023
11/30/2023 RSBU - Building Final N/A Re-inspection required Called multiple times and left voicemails. Received a call back and was told it was the wrong number. Got to the site and gates were locked. Dogs are on site. Provide access to the site. 11/30/2023
11/30/2023 COT - RSOL - Electrical Final Solar Project N/A Re-inspection required Called multiple times and left voicemails. Received a call back and was told it was the wrong number. Got to the site and gates were locked. Dogs are on site. Provide access to the site. 11/30/2023
11/30/2023 COT - RSOL - Grounding/Bonding Solar Project N/A Re-inspection required

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-0923-08178
Permit Description: Installation of a new roof mounted 11.68 kw solar PV system. 32 modules
Total Completed Inspections - 4
Date Description Inspector Results Comments
12/08/2023 BULD - Electrical Clearance Passed Approved solar install, DGC Clearance to TEP is required for the solar meter
12/08/2023 RSBU - Building Final Passed
12/08/2023 COT - RSOL - Electrical Final Solar Project Passed
12/08/2023 COT - RSOL - Grounding/Bonding Solar Project Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-DIAZ J_DWG BINDER_091423 (1)_V1.PDF DOCUMENTS VIEW