Permit: TC-RES-0725-03718
Permit Details
Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address:
1023 N 1ST AV UNIT 2
Address NEW:
1023 N 1ST AV UNIT 2
Apply Date:
07/28/2025
Applicant:
Jesus Torres
Description:
ADU
Permit Reviews
Permit Number - TC-RES-0725-03718
Permit Status: Inspections complete
Permit Description: ADU
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/18/2025 | ADMINISTRATIVE v.1 | 12/18/2025 | REQUIRES RESUBMIT |
| 07/28/2025 | RESIDENTIAL ADU v.1 | 08/26/2025 | REQUIRES RESUBMIT |
| 12/09/2025 | RESIDENTIAL ADU v.2 | 12/18/2025 | APPROVED |
| 12/18/2025 | ADMINISTRATIVE v.2 | 12/18/2025 | APPROVED |
Conditions
Permit Number - TC-RES-0725-03718
Permit Status: Inspections complete
Permit Description: ADU
| Date | Description | Comments |
|---|---|---|
| 07/28/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. | |
| 12/09/2025 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0725-03718
Permite Description: ADU
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/17/2026 | COT - RSPL - Yard Water Line | N/A | Canceled | |
| 09/17/2026 | COT - RSEL - Electrical Final | N/A | Re-inspection required | Please call after power is restored 09/17/2026 AC breaker is over-amped, requires a max 30A fuse. Paint exposed plastic vent pipes. Add smoke detector to bedroom. Secure AC electrical whip to wall. Add AFCI breakers to all habitable rooms, hallway, kitchen and living room area circuits at main panel and label all breakers. Laundry room receptacle needs to be GFCI. |
| 09/17/2026 | RSBU - Building Final | N/A | Re-inspection required | Please call after power is restored 09/17/2026 AC breaker is over-amped, requires a max 30A fuse. Paint exposed plastic vent pipes. Add smoke detector to bedroom. Secure AC electrical whip to wall. Add AFCI breakers to all habitable rooms, hallway, kitchen and living room area circuits at main panel and label all breakers. Laundry room receptacle needs to be GFCI. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0725-03718
Permit Description: ADU
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/28/2026 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Ok to place concrete for stem walls. | |
| 01/28/2026 | COT - RSPL - Rough Soil | Passed | ||
| 01/28/2026 | COT - RSEL - Grounding/Bonding | Passed | ||
| 02/06/2026 | COT - RSBU - Preslab | Passed | Passed 2/6/26 | |
| 03/11/2026 | COT - RSBU - Roof Nailing | Passed | ||
| 03/20/2026 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Corrections made Approved |
|
| 03/20/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 3.20.26 DWV under pressure Lines secured Penetrations sealed Box spacing verified Approved |
|
| 04/17/2026 | BULD - Electrical Clearance | Passed | Passed 4/17/26 CLEARANCE ECO UNIT 2 | |
| 08/24/2026 | COT - RSPL - Yard Water Line | Passed | ||
| 09/17/2026 | COT - RSEL - Outdoor Lighting | Passed | ||
| 09/17/2026 | COT - RSME - Mechanical Final | Passed | ||
| 09/17/2026 | COT - RSPL - Plumbing Final | Passed | ||
| 09/22/2026 | COT - RSEL - Electrical Final | Passed | 09/22/2026 Corrections made. |
|
| 09/24/2026 | RSBU - Building Final | Passed | 09/24/2026 Uploaded truss calcs/design to satisfy remaining open condition - see attachment. |