Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address NEW:
513 S CATALINA AV
Apply Date:
07/19/2023
Applicant:
Russell Noon
Description:
Garage

Permit Reviews

Permit Number - TC-RES-0723-06650
Permit Status: Complete
Permit Description: Garage
Start Date Submittal Complete Date Status  
07/24/2023 RESIDENTIAL NEW DWELLING v.1 08/09/2023 REQUIRES RESUBMIT Review Details
12/15/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/23/2024 APPROVED Review Details
09/01/2023 RESIDENTIAL NEW DWELLING v.2 09/26/2023 REQUIRES RESUBMIT Review Details
10/31/2023 RESIDENTIAL NEW DWELLING v.3 11/15/2023 APPROVED Review Details

Conditions

Permit Number - TC-RES-0723-06650
Permit Status: Complete
Permit Description: Garage
Date Description Comments
11/15/2023 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as a contact. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
08/09/2023 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-0723-06650
Permit Description: Garage
Total Completed Inspections - 8
Date Description Inspector Results Comments
12/11/2023 COT - RSEL - Grounding/Bonding Passed Ufer ground is properly connected to a 20' piece of rebar reinforcement in the bottom of footer.
12/11/2023 COT - RSBU - Preslab Passed Subsoil is properly compacted, forms are in place, rebar is properly supported, and Ufer ground is installed. Okay to pour concrete.
12/11/2023 COT - RSBU - Excavation/Rebar/Zoning Passed Rebar reinforcement is properly installed.
01/26/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Exterior walls are framed out, roof trusses are installed and properly clipped with Simpson clips. Okay to proceed with shear panels and roof sheathing.
02/23/2024 COT - RSBU - Roof Nailing Passed
02/23/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
05/23/2024 COT - RSBU - Firewall/Fire Barrier/Firestop Passed
11/15/2024 RSBU - Building Final Passed

Documents

File Name Document Type  
TRUSS ENGINEERING_SIGNED-STAMPED_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
OWNER-BUILDER_AFFIDAVIT_R.NOON_V1.PDF DOCUMENTS VIEW
COMPLETE SITE PLAN_V.3_V2.PDF DOCUMENTS VIEW