Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address:
7771 E LESTER ST
Address NEW:
7771 E LESTER ST
Apply Date:
06/18/2025
Applicant:
Aaron Skoczen
Description:
REV1: A3 – Foundation Plan Current drawings call out for Simpson PAHD42 hold down straps, which have been discontinued and no longer manufactured. We exchanged these for Simpson LSTHD8 Stap-Tie Hold downs, which carry a greater tension load. Please see attached for the LSTHD8 spec sheet. We were unable to find a copy of the PAHD42 spec sheet from Simpson Strong Tie. A1-Plan Current drawings call out SW gas line running from the north side of the property to the existing structure. Southwest Gas would like to relocate the meter and run new lines. We marked the approximate location of the new lines that run from the alley on the north side of the property along the west setback space and connect to the new meter on the West side of the house. We will then tap into it to provide gas to the structure. Master Suite Addition

Permit Reviews

Permit Number - TC-RES-0625-03093
Permit Status: Complete
Permit Description: REV1: A3 – Foundation Plan Current drawings call out for Simpson PAHD42 hold down straps, which have been discontinued and no longer manufactured. We exchanged these for Simpson LSTHD8 Stap-Tie Hold downs, which carry a greater tension load. Please see attached for the LSTHD8 spec sheet. We were unable to find a copy of the PAHD42 spec sheet from Simpson Strong Tie. A1-Plan Current drawings call out SW gas line running from the north side of the property to the existing structure. Southwest Gas would like to relocate the meter and run new lines. We marked the approximate location of the new lines that run from the alley on the north side of the property along the west setback space and connect to the new meter on the West side of the house. We will then tap into it to provide gas to the structure. Master Suite Addition
Start Date Submittal Complete Date Status  
07/24/2025 RESIDENTIAL ADD/ALT v.2 07/30/2025 APPROVED Review Details
07/30/2025 RESTAMP - RESIDENTIAL v.1 07/30/2025 APPROVED Review Details
11/13/2025 RESIDENTIAL NEW DWELLING REVISION v.2 11/21/2025 APPROVED Review Details
06/18/2025 RESIDENTIAL ADD/ALT v.1 07/23/2025 REQUIRES RESUBMIT Review Details
11/06/2025 RESIDENTIAL NEW DWELLING REVISION v.1 11/06/2025 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-RES-0625-03093
Permit Status: Complete
Permit Description: REV1: A3 – Foundation Plan Current drawings call out for Simpson PAHD42 hold down straps, which have been discontinued and no longer manufactured. We exchanged these for Simpson LSTHD8 Stap-Tie Hold downs, which carry a greater tension load. Please see attached for the LSTHD8 spec sheet. We were unable to find a copy of the PAHD42 spec sheet from Simpson Strong Tie. A1-Plan Current drawings call out SW gas line running from the north side of the property to the existing structure. Southwest Gas would like to relocate the meter and run new lines. We marked the approximate location of the new lines that run from the alley on the north side of the property along the west setback space and connect to the new meter on the West side of the house. We will then tap into it to provide gas to the structure. Master Suite Addition
Date Description Comments
06/18/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-RES-0625-03093
Permite Description: REV1: A3 – Foundation Plan Current drawings call out for Simpson PAHD42 hold down straps, which have been discontinued and no longer manufactured. We exchanged these for Simpson LSTHD8 Stap-Tie Hold downs, which carry a greater tension load. Please see attached for the LSTHD8 spec sheet. We were unable to find a copy of the PAHD42 spec sheet from Simpson Strong Tie. A1-Plan Current drawings call out SW gas line running from the north side of the property to the existing structure. Southwest Gas would like to relocate the meter and run new lines. We marked the approximate location of the new lines that run from the alley on the north side of the property along the west setback space and connect to the new meter on the West side of the house. We will then tap into it to provide gas to the structure. Master Suite Addition
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
10/08/2025 COT - RSBU - Preslab N/A Not Ready Per builder; Ken will approve installed holddowns in lieu of specified holddowns; pour at own risk.

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-0625-03093
Permit Description: REV1: A3 – Foundation Plan Current drawings call out for Simpson PAHD42 hold down straps, which have been discontinued and no longer manufactured. We exchanged these for Simpson LSTHD8 Stap-Tie Hold downs, which carry a greater tension load. Please see attached for the LSTHD8 spec sheet. We were unable to find a copy of the PAHD42 spec sheet from Simpson Strong Tie. A1-Plan Current drawings call out SW gas line running from the north side of the property to the existing structure. Southwest Gas would like to relocate the meter and run new lines. We marked the approximate location of the new lines that run from the alley on the north side of the property along the west setback space and connect to the new meter on the West side of the house. We will then tap into it to provide gas to the structure. Master Suite Addition
Total Completed Inspections - 15
Date Description Inspector Results Comments
10/02/2025 COT - RSPL - Sewer Passed Passed 10/2/25 ok to backfill
11/05/2025 COT - RSBU - Roof Nailing Passed
11/25/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed 11-25-25: previously inspected.
RFI for hold-downs has been submitted to the city.
11/28/2025 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 11.28.25
APPROVED
12/10/2025 COT - BULD - SWG Clearance Passed swg
existing meter is being moved
12/11/2025 BULD - Electrical Clearance Passed 12.11.25
Corrections made
Approved for INCR
01/12/2026 COT - RSEL - Electrical Underground Passed
03/09/2026 RSBU - Building Final Passed
03/09/2026 COT - RSBU - Excavation/Rebar/Zoning Passed
03/09/2026 COT - RSEL - Electrical Final Passed
03/09/2026 COT - RSPL - Yard Water Line Passed
03/09/2026 COT - RSEL - Grounding/Bonding Passed
03/09/2026 COT - RSME - Mechanical Final Passed
03/09/2026 COT - RSPL - Rough Soil Passed
03/11/2026 COT - RSPL - Plumbing Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-REV1_PLAN SET_RASTATTER_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW