Permit: TC-RES-0625-02952
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
4749 E COPPER ST
Address NEW:
4749 E COPPER ST
Apply Date:
06/09/2025
Applicant:
TFS Solar
Description:
13.5 kWh storage addition. Single Tesla Powerwall-3 battery added to existing solar PV system. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup. 60A PCS breaker for battery interconnection. Existing 30A PV interconnection breaker.
Permit Reviews
Permit Number - TC-RES-0625-02952
Permit Status: Complete
Permit Description: 13.5 kWh storage addition. Single Tesla Powerwall-3 battery added to existing solar PV system. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup. 60A PCS breaker for battery interconnection. Existing 30A PV interconnection breaker.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/09/2025 | RESIDENTIAL SOLAR v.1 | 07/01/2025 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0625-02952
Permit Description: 13.5 kWh storage addition. Single Tesla Powerwall-3 battery added to existing solar PV system. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup. 60A PCS breaker for battery interconnection. Existing 30A PV interconnection breaker.
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/28/2025 | BULD - Electrical Clearance | Passed | 8.28.25 Tesla Powerwall 3 added to existing system. BAT clearance to TEP. |
|
| 08/28/2025 | COT - RSOL - Electrical Final Solar Project | Passed | 8.28.25 Tesla Powerwall 3 added to existing system. BAT clearance to TEP. |