Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address NEW:
3003 E 3RD ST UNIT 2
Apply Date:
06/02/2024
Applicant:
James and Cynthia Broderick
Description:
ADU as part of a larger project on the property. Proposed project will require DDO. Drawings submitted are part of anticipated DDO submittal documents.

Permit Reviews

Permit Number - TC-RES-0624-03329
Permit Status: Complete
Permit Description: ADU as part of a larger project on the property. Proposed project will require DDO. Drawings submitted are part of anticipated DDO submittal documents.
Start Date Submittal Complete Date Status  
08/20/2024 RESIDENTIAL NEW DWELLING v.3 09/16/2024 REQUIRES RESUBMIT Review Details
08/19/2024 RESIDENTIAL NEW DWELLING v.2 08/19/2024 REQUIRES RESUBMIT Review Details
04/17/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/17/2026 APPROVED Review Details
05/13/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/16/2025 APPROVED Review Details
06/03/2024 RESIDENTIAL NEW DWELLING v.1 06/18/2024 REQUIRES RESUBMIT Review Details
03/27/2025 RESIDENTIAL NEW DWELLING v.1 04/29/2025 APPROVED Review Details
03/03/2025 RESIDENTIAL NEW DWELLING v.4 03/17/2025 APPROVED Review Details

Conditions

Permit Number - TC-RES-0624-03329
Permit Status: Complete
Permit Description: ADU as part of a larger project on the property. Proposed project will require DDO. Drawings submitted are part of anticipated DDO submittal documents.
Date Description Comments
06/03/2024 Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512
03/03/2025 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
04/22/2025 Manual J report
03/03/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-RES-0624-03329
Permite Description: ADU as part of a larger project on the property. Proposed project will require DDO. Drawings submitted are part of anticipated DDO submittal documents.
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
10/06/2025 COT - RSPL - Plumbing Final N/A Not Ready 10.6.2025
Not ready.
10/17/2025 COT - RSEL - Grounding/Bonding N/A Partial Pass Partial pass. Pending tie into panel. 10/17/2025

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-0624-03329
Permit Description: ADU as part of a larger project on the property. Proposed project will require DDO. Drawings submitted are part of anticipated DDO submittal documents.
Total Completed Inspections - 15
Date Description Inspector Results Comments
08/20/2025 COT - RSEL - Electrical Underground Passed
08/20/2025 COT - RSPL - Rough Soil Passed Ok to cover progress areas.
08/20/2025 COT - RSPL - Yard Water Line Passed
10/17/2025 COT - RSBU - Excavation/Rebar/Zoning Passed
10/17/2025 COT - RSBU - Preslab Passed
11/19/2025 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed
01/14/2026 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed 1.14.26
Approved
02/18/2026 BULD - Electrical Clearance Passed Passer CLEARANCE INCR 2/18/26
04/07/2026 RSBU - Building Final Passed
04/07/2026 COT - RSME - Mechanical Final Passed
04/07/2026 COT - RSEL - Electrical Final Passed
04/07/2026 COT - RSPL - Plumbing Final Passed
04/07/2026 COT - RSEL - Outdoor Lighting Passed
04/08/2026 COT - RSBU - Roof Nailing Passed
04/08/2026 COT - RSEL - Grounding/Bonding Passed

Documents

File Name Document Type  
BRODERICK HVAC SUBMITTAL_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-BRODERICK_ADU_V3.PDF DOCUMENTS VIEW
CONS-BRODERICK_ADU_V3.PDF DOCUMENTS VIEW
DDO-24-82 DECISION.PDF SPECIAL APPLICATIONS VIEW
DDO-24-82 APPLICATION AND PLAN SET.PDF SPECIAL APPLICATIONS VIEW
DDO-24-82 NOTICE.PDF SPECIAL APPLICATIONS VIEW