Permit: TC-RES-0524-02824
Permit Details
Status:
Inspections
Type:
Residential Building - One or Two Family
Address:
2320 S HARRISON RD
Address NEW:
2320 S HARRISON RD
Apply Date:
05/08/2024
Applicant:
Frank Corso
Description:
Replace Porch with Storage Room
Permit Reviews
Permit Number - TC-RES-0524-02824
Permit Status: Inspections
Permit Description: Replace Porch with Storage Room
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/10/2024 | RESIDENTIAL NEW DWELLING v.1 | 06/10/2024 | APPROVED |
| 08/13/2024 | RESIDENTIAL NEW DWELLING REVISION v.1 | 08/22/2024 | APPROVED |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-RES-0524-02824
Permite Description: Replace Porch with Storage Room
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/08/2024 | COT - RSBU - Preslab | N/A | Re-inspection required | No rebar reinforcement is in concrete footing or slab, subsoil has too many large rocks and pieces of concrete, existing concrete slab needs to have holes or key ways to keep new slab from moving on top of old slab. Subsoil needs to be compacted. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-RES-0524-02824
Permit Description: Replace Porch with Storage Room
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/10/2024 | COT - RSBU - Preslab | Passed | 7/10/24: Rebar reinforcement has been installed in footing and is properly supported off of ground. Existing slab has been drilled and rebar secured into holes. Okay to proceed with concrete pour. | |
| 07/10/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | 7/10/24: Rebar reinforcement has been installed in footing and is properly supported off of ground. Okay to proceed with concrete pour. | |
| 07/30/2024 | COT - RSBU - Masonry Pregrout | Passed | 7/30/24: okay to grout and cap final lift | |
| 08/06/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 08/06/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 08/23/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Electrical rough-in is complete. Okay to proceed with insulation and drywall work. | |
| 09/13/2024 | RSBU - Building Final | Passed | Construction is complete per plan. Okay to issue Certificate of Completion. | |
| 09/13/2024 | COT - RSEL - Electrical Final | Passed | Construction is complete per plan. Okay to issue Certificate of Completion. |