Permit Details

Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2625 E CLAYS AL
Address NEW:
2625 E CLAYS AL
Apply Date:
05/07/2023
Applicant:
Description:
Remodel SFR and Enclose Garage into Bedrooms and Bathroom

Permit Reviews

Permit Number - TC-RES-0523-04991
Permit Status: Complete
Permit Description: Remodel SFR and Enclose Garage into Bedrooms and Bathroom
Start Date Submittal Complete Date Status  
07/03/2023 RESIDENTIAL NEW DWELLING v.2 07/06/2023 APPROVED Review Details
05/08/2023 RESIDENTIAL NEW DWELLING v.1 06/13/2023 REQUIRES RESUBMIT Review Details
07/06/2023 RESTAMP - RESIDENTIAL v.1 07/07/2023 APPROVED Review Details

Conditions

Permit Number - TC-RES-0523-04991
Permit Status: Complete
Permit Description: Remodel SFR and Enclose Garage into Bedrooms and Bathroom
Date Description Comments
07/07/2023 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/integrated-planning/PDSD/PDSD_Owner_Builder_Affidavit.pdf, is required prior to issuance of permit.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-RES-0523-04991
Permite Description: Remodel SFR and Enclose Garage into Bedrooms and Bathroom
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
09/26/2023 COT - RSPL - Rough Soil N/A Partial Pass 1-exterior lines are less than 12" deep(P2603.5.1, as amended). 2-Water piping outside needs tracer wire. 3-Protect water piping at stem wall per P2603.4. OK to proceed elsewhere.
02/06/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. N/A Not Ready 2/6/2024 Not ready. Add three receptacles in master bedroom. Move over receptacle in kitchen. Block all registers on three sides. Install exhaust fans. Add treated wood where needed throughout home. Secure treated wood. Add nail plates at any lines less than an 1"1/4. Provide DWV throughout home. Secure ABS lines. Add vents for both kitchen hood and dryer. (Solid)
Gas lines would be installed at a later date on the roof and need to have pressure test.
07/30/2024 RSBU - Building Final N/A Not Ready No gate code.
10/21/2024 COT - RSME - Mechanical Final N/A Not Ready
10/21/2024 COT - RSPL - Plumbing Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: TC-RES-0523-04991
Permit Description: Remodel SFR and Enclose Garage into Bedrooms and Bathroom
Total Completed Inspections - 13
Date Description Inspector Results Comments
10/03/2023 COT - RSPL - Rough Soil Passed 10/3/23: all corrections made okay to proceed with backfill and concrete
11/15/2023 COT - RSBU - Excavation/Rebar/Zoning Passed Footing for new addition is properly dug, rebar reinforcement is installed correctly. Okay to pour concrete footing and slab on grade.
11/15/2023 BULD - Electrical Clearance Passed Electrical panel and meter box are installed. Okay to energize. ECO Clearance issued for new service.
12/08/2023 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed Roof framing is complete, exterior walls are properly framing and secured to concrete floor. Okay to proceed with exterior stucco application and roofing work.
02/28/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Foyer and laundry areas approved. 2/28/2024
03/04/2024 COT - RSEL - Grounding/Bonding Passed
04/22/2024 COT - RSPL - Gas Pressure Test Passed 4/22/24: New gas lines have been ran to new a/c units and to water heater. Gas line is pressurized to 15# of air pressure and holding without leaks. Full pass and SWG Clearance given.
04/22/2024 COT - BULD - SWG Clearance Passed 4/22/24: New gas lines have been ran to new a/c units and to water heater. Gas line is pressurized to 15# of air pressure and holding without leaks. Full pass and SWG Clearance given.
08/07/2024 RSBU - Building Final Passed
10/23/2024 COT - RSME - Mechanical Final Passed
10/23/2024 COT - RSPL - Plumbing Final Passed
10/23/2024 COT - RSEL - Electrical Final Passed
12/06/2024 RSBU - Building Progress Passed

Documents

File Name Document Type  
LOFC_LETTEROFCOMPLETION.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONTRACTOR LETTER 2625.PDF DOCUMENTS VIEW
202K23 CLAYS REV_V1.PDF DOCUMENTS VIEW