Permit: TC-RES-0523-04991
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2625 E CLAYS AL
Address NEW:
2625 E CLAYS AL
Apply Date:
05/07/2023
Applicant:
Description:
Remodel SFR and Enclose Garage into Bedrooms and Bathroom
Permit Reviews
Permit Number - TC-RES-0523-04991
Permit Status: Complete
Permit Description: Remodel SFR and Enclose Garage into Bedrooms and Bathroom
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/03/2023 | RESIDENTIAL NEW DWELLING v.2 | 07/06/2023 | APPROVED |
| 05/08/2023 | RESIDENTIAL NEW DWELLING v.1 | 06/13/2023 | REQUIRES RESUBMIT |
| 07/06/2023 | RESTAMP - RESIDENTIAL v.1 | 07/07/2023 | APPROVED |
Conditions
Permit Number - TC-RES-0523-04991
Permit Status: Complete
Permit Description: Remodel SFR and Enclose Garage into Bedrooms and Bathroom
| Date | Description | Comments |
|---|---|---|
| 07/07/2023 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/integrated-planning/PDSD/PDSD_Owner_Builder_Affidavit.pdf, is required prior to issuance of permit. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-RES-0523-04991
Permite Description: Remodel SFR and Enclose Garage into Bedrooms and Bathroom
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/26/2023 | COT - RSPL - Rough Soil | N/A | Partial Pass | 1-exterior lines are less than 12" deep(P2603.5.1, as amended). 2-Water piping outside needs tracer wire. 3-Protect water piping at stem wall per P2603.4. OK to proceed elsewhere. |
| 02/06/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | 2/6/2024 Not ready. Add three receptacles in master bedroom. Move over receptacle in kitchen. Block all registers on three sides. Install exhaust fans. Add treated wood where needed throughout home. Secure treated wood. Add nail plates at any lines less than an 1"1/4. Provide DWV throughout home. Secure ABS lines. Add vents for both kitchen hood and dryer. (Solid) Gas lines would be installed at a later date on the roof and need to have pressure test. |
| 07/30/2024 | RSBU - Building Final | N/A | Not Ready | No gate code. |
| 10/21/2024 | COT - RSME - Mechanical Final | N/A | Not Ready | |
| 10/21/2024 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0523-04991
Permit Description: Remodel SFR and Enclose Garage into Bedrooms and Bathroom
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/03/2023 | COT - RSPL - Rough Soil | Passed | 10/3/23: all corrections made okay to proceed with backfill and concrete | |
| 11/15/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | Footing for new addition is properly dug, rebar reinforcement is installed correctly. Okay to pour concrete footing and slab on grade. | |
| 11/15/2023 | BULD - Electrical Clearance | Passed | Electrical panel and meter box are installed. Okay to energize. ECO Clearance issued for new service. | |
| 12/08/2023 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | Roof framing is complete, exterior walls are properly framing and secured to concrete floor. Okay to proceed with exterior stucco application and roofing work. | |
| 02/28/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | Foyer and laundry areas approved. 2/28/2024 | |
| 03/04/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 04/22/2024 | COT - RSPL - Gas Pressure Test | Passed | 4/22/24: New gas lines have been ran to new a/c units and to water heater. Gas line is pressurized to 15# of air pressure and holding without leaks. Full pass and SWG Clearance given. | |
| 04/22/2024 | COT - BULD - SWG Clearance | Passed | 4/22/24: New gas lines have been ran to new a/c units and to water heater. Gas line is pressurized to 15# of air pressure and holding without leaks. Full pass and SWG Clearance given. | |
| 08/07/2024 | RSBU - Building Final | Passed | ||
| 10/23/2024 | COT - RSME - Mechanical Final | Passed | ||
| 10/23/2024 | COT - RSPL - Plumbing Final | Passed | ||
| 10/23/2024 | COT - RSEL - Electrical Final | Passed | ||
| 12/06/2024 | RSBU - Building Progress | Passed |