Permit Details

Status:
Inspections
Type:
Residential Building - One or Two Family
Apply Date:
05/05/2023
Applicant:
George Zazueta
Description:
2nd Dwelling Unit

Permit Reviews

Permit Number - TC-RES-0523-04983
Permit Status: Inspections
Permit Description: 2nd Dwelling Unit
Start Date Submittal Complete Date Status  
07/09/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 N/A REQUIRES RESUBMIT Review Details
06/17/2024 RESTAMP - RESIDENTIAL v.1 06/20/2024 APPROVED Review Details
05/08/2023 RESIDENTIAL NEW DWELLING v.1 06/13/2023 REQUIRES RESUBMIT Review Details
09/26/2023 RESIDENTIAL NEW DWELLING v.2 10/17/2023 REQUIRES RESUBMIT Review Details
08/18/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.2 N/A REQUIRES RESUBMIT Review Details
05/22/2024 RESIDENTIAL NEW DWELLING v.4 06/14/2024 APPROVED Review Details
08/25/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.3 08/28/2026 APPROVED Review Details
11/03/2023 RESIDENTIAL NEW DWELLING v.3 11/15/2023 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-RES-0523-04983
Permit Status: Inspections
Permit Description: 2nd Dwelling Unit
Date Description Comments
06/20/2024 Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/permits/residential-permits/pdsd_owner_builder_affidavit_081623.pdf, is required prior to issuance of permit. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit.
06/13/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
08/06/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-RES-0523-04983
Permite Description: 2nd Dwelling Unit
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
11/13/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing N/A Partial Pass 11/13/24 pass. Exterior sheathing and clip is to schedule. No truss schedule on site.
01/27/2025 RSBU - Building Final N/A Re-inspection required 1-27-25, paint/coat all exterior plastic, install hammer arrestor on dishwasher, lower thermostat to a height of 54".
01/27/2025 COT - RSME - Mechanical Final N/A Not Ready 1-27-25, unable to verify operation of hvac because unit has no power.
01/27/2025 COT - RSPL - Plumbing Final N/A Re-inspection required 1-27-25, paint/coat all exterior plastic, install hammer arrestor on dishwasher, lower thermostat to a height of 54".
01/27/2025 COT - RSEL - Electrical Final N/A Not Ready 1-27-25, not ready. Unit currently has no power, however, I verified that all receptacles/smoke detectors are installed per approved plans.

Completed Inspections

Permit Status: Inspections
Permit Number: TC-RES-0523-04983
Permit Description: 2nd Dwelling Unit
Total Completed Inspections - 14
Date Description Inspector Results Comments
09/16/2024 COT - RSPL - Rough Soil Passed
09/19/2024 COT - RSBU - Excavation/Rebar/Zoning Passed
09/19/2024 COT - RSBU - Preslab Passed
09/20/2024 COT - RSEL - Grounding/Bonding Passed Approved ufer ground to rebar, okay to pour
10/31/2024 COT - RSBU - Roof Nailing Passed OK to dry-in roof system.
11/15/2024 COT - RSBU - Exterior/Interior Clips/Sheathing/Framing Passed passed 11/15/24
11/25/2024 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed Ok to insulate and cover walls.
01/27/2025 BULD - Electrical Clearance Passed 1-27-25, panel approved to be energized. ECO clearance sent to TEP.
01/27/2025 COT - RSPL - Sewer Passed 1-27-25, approved.
01/27/2025 COT - RSPL - Yard Water Line Passed 1-27-25, main water line approved. Okay to backfill trench.
02/06/2025 RSBU - Building Final Passed 2/6/25 pass
02/06/2025 COT - RSME - Mechanical Final Passed 2/6/25 pass
02/06/2025 COT - RSPL - Plumbing Final Passed 2/6/25 pass
02/06/2025 COT - RSEL - Electrical Final Passed 2/6/25 pass

Documents

File Name Document Type  
1460 DELWARE CALC2_V1.PDF DOCUMENTS VIEW
PERMIT CARD.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
OBA_V1.PDF DOCUMENTS VIEW
CONS-TC-RES-0523-04983_PLAN_SET_2_V3.PDF DOCUMENTS VIEW
CONS-TC-RES-0523-04983_PLAN_SET_2_V3.PDF DOCUMENTS VIEW