Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-RES-0425-01807
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
7664 S LIONS SPRING WY
Address NEW:
7664 S LIONS SPRING WY
Apply Date:
04/07/2025
Applicant:
TFS Solar
Description:
Roof mount 7.83 kW DC photovoltaic solar system; 18 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Permit Reviews
Permit Number - TC-RES-0425-01807
Permit Status: Complete
Permit Description: Roof mount 7.83 kW DC photovoltaic solar system; 18 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/10/2025 | RESIDENTIAL SOLAR v.1 | 05/12/2025 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0425-01807
Permit Description: Roof mount 7.83 kW DC photovoltaic solar system; 18 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 2 strings. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/14/2025 | BULD - Electrical Clearance | Passed | 8.14.25 DGC/BAT PV system verified as per plans Approved |
|
| 08/14/2025 | RSBU - Building Final | Passed | 8.14.25 DGC/BAT PV system verified as per plans Approved |
|
| 08/14/2025 | COT - RSOL - Electrical Final Solar Project | Passed | 8.14.25 DGC/BAT PV system verified as per plans Approved |