Permit: TC-RES-0424-02472
Permit Details
Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address:
2406 E HAWTHORNE ST UNIT 2
Address NEW:
2406 E HAWTHORNE ST UNIT 2
Apply Date:
04/24/2024
Applicant:
Description:
REV 1: New site wall segment to replace existing wall segment found unsafe Convert Expanded Garage into ADU; Screen Wall and Shade Structure
Permit Reviews
Permit Number - TC-RES-0424-02472
Permit Status: Inspections complete
Permit Description: REV 1: New site wall segment to replace existing wall segment found unsafe
Convert Expanded Garage into ADU; Screen Wall and Shade Structure
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/06/2026 | RESTAMP - RESIDENTIAL v.1 | 04/07/2026 | APPROVED |
| 04/26/2024 | RESIDENTIAL NEW DWELLING v.1 | 05/28/2024 | REQUIRES RESUBMIT |
| 10/07/2025 | RESIDENTIAL NEW DWELLING REVISION v.1 | 10/07/2025 | REQUIRES RESUBMIT |
| 09/26/2025 | RESIDENTIAL ADU v.1 | 10/06/2025 | APPROVED |
| 10/09/2024 | RESIDENTIAL NEW DWELLING v.3 | 11/13/2024 | APPROVED |
| 07/18/2024 | RESIDENTIAL NEW DWELLING v.2 | 08/19/2024 | REQUIRES RESUBMIT |
| 10/08/2025 | RESIDENTIAL NEW DWELLING REVISION v.2 | 10/10/2025 | APPROVED |
Conditions
Permit Number - TC-RES-0424-02472
Permit Status: Inspections complete
Permit Description: REV 1: New site wall segment to replace existing wall segment found unsafe
Convert Expanded Garage into ADU; Screen Wall and Shade Structure
| Date | Description | Comments |
|---|---|---|
| 05/09/2024 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 | |
| 10/06/2025 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0424-02472
Permite Description: REV 1: New site wall segment to replace existing wall segment found unsafe
Convert Expanded Garage into ADU; Screen Wall and Shade Structure
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/11/2025 | COT - RSBU - Stem Wall/Retaining Wall | N/A | Partial Pass | |
| 09/11/2025 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Partial Pass | 9/11/2025 partial pass. Mechanical in place okay to proceed progress areas. |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0424-02472
Permit Description: REV 1: New site wall segment to replace existing wall segment found unsafe
Convert Expanded Garage into ADU; Screen Wall and Shade Structure
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/29/2025 | COT - RSPL - Rough Soil | Passed | OK to cover progress areas. | |
| 01/29/2025 | COT - RSPL - Yard Water Line | Passed | OK to cover progress area. | |
| 03/20/2025 | COT - RSEL - Electrical Underground | Passed | ||
| 03/26/2025 | COT - RSBU - Preslab | Passed | Ok to place concrete for the ADU slab. | |
| 04/02/2025 | COT - RSBU - Excavation/Rebar/Zoning | Passed | In wall rebar as per plans. Ok to grout progress areas. | |
| 07/09/2025 | COT - RSBU - Masonry Pregrout | Passed | 7/9/2025 fox block at top out and fully grouted. | |
| 07/09/2025 | COT - RSBU - Roof Nailing | Passed | ||
| 07/09/2025 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 03/05/2026 | COT - RSBU - Sustainability | Passed | ||
| 03/05/2026 | COT - RSBU - Stem Wall/Retaining Wall | Passed | ||
| 03/05/2026 | COT - RSEL - Electrical Final | Passed | ||
| 03/05/2026 | COT - RSEL - Outdoor Lighting | Passed | ||
| 03/05/2026 | COT - RSME - Mechanical Final | Passed | ||
| 03/12/2026 | COT - RSPL - Gas Pressure Test | Passed | ||
| 03/12/2026 | COT - BULD - SWG Clearance | Passed | ||
| 03/18/2026 | COT - RSPL - Plumbing Final | Passed | 3.18.26 Approved via on site inspection and photos |
|
| 03/18/2026 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | 3.18.26 Approved via on site inspection and photos |
|
| 04/13/2026 | RSBU - Building Final | Passed | 4/13/26 passed |