Permit: TC-RES-0223-03154
Permit Details
Apply Date:
02/27/2023
Applicant:
Shawn Hunter
Description:
Renovate SFR and Sleeping Quarters Addition
Permit Reviews
Permit Number - TC-RES-0223-03154
Permit Status: Issued
Permit Description: Renovate SFR and Sleeping Quarters Addition
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/26/2023 | RESIDENTIAL NEW DWELLING v.2 | 05/17/2023 | REQUIRES RESUBMIT |
05/26/2023 | RESIDENTIAL NEW DWELLING v.4 | 06/07/2023 | APPROVED |
06/07/2023 | RESTAMP - RESIDENTIAL v.1 | 06/07/2023 | APPROVED |
02/28/2023 | RESIDENTIAL NEW DWELLING v.1 | 03/28/2023 | REQUIRES RESUBMIT |
05/24/2023 | RESIDENTIAL NEW DWELLING v.3 | 05/24/2023 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-RES-0223-03154
Permite Description: Renovate SFR and Sleeping Quarters Addition
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/08/2023 | RSEL - Electrical Progress | N/A | Partial Pass | |
08/08/2023 | RSME - Mechanical Progress | N/A | Not Ready | |
08/08/2023 | BULD - Electrical Clearance | N/A | Not Ready | |
08/08/2023 | COT - RSBU - Interior Shear Bracing | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: TC-RES-0223-03154
Permit Description: Renovate SFR and Sleeping Quarters Addition
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/09/2023 | COT - RSPL - Sewer | Passed | Sewer line is ran from the house and connected to main sewer line. Okay to backfill trenches. | |
06/09/2023 | COT - RSPL - Rough Soil | Passed | 6-9-23: Plumbers have installed water column at 5', all underground plumbing is under water test. Okay to backfill trenches and prepare for subsoil compaction. | |
06/20/2023 | COT - RSBU - Preslab | Passed | ||
08/22/2023 | BULD - Electrical Clearance | Passed | TEP ECO | |
08/22/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
10/05/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | Inspection was for drywall sheathing. Approved . Okay for tape and mud. 10/5/2023 | |
10/05/2023 | COT - RSBU - Interior Shear Bracing | Passed | Approved . Okay for tape and mud. 10/5/2023 | |
12/20/2023 | RSBU - Building Final | Passed | Contractor will submit letter stating that all work will be completed per Code. | |
01/04/2024 | COT - RSPL - Gas Pressure Test | Passed | ||
01/04/2024 | COT - BULD - SWG Clearance | Passed | Clearance for Southwest Gas. 1/4/2024 |