Permit: TC-RES-0126-00263
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
860 N STONER AV
Address NEW:
860 N STONER AV
Apply Date:
01/20/2026
Applicant:
Marytine Ramos
Description:
REV_1, Equipment relocation; Installation of 9.02 kW PV System with SE battery and 225A MPU
Permit Reviews
Permit Number - TC-RES-0126-00263
Permit Status: Complete
Permit Description: REV_1, Equipment relocation; Installation of 9.02 kW PV System with SE battery and 225A MPU
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/02/2026 | RESIDENTIAL SOLAR REVISION v.1 | 04/15/2026 | REQUIRES RESUBMIT |
| 04/16/2026 | RESIDENTIAL SOLAR REVISION v.2 | 04/21/2026 | APPROVED |
| 01/21/2026 | RESIDENTIAL SOLAR v.1 | 01/28/2026 | APPROVED |
Conditions
Permit Number - TC-RES-0126-00263
Permit Status: Complete
Permit Description: REV_1, Equipment relocation; Installation of 9.02 kW PV System with SE battery and 225A MPU
| Date | Description | Comments |
|---|---|---|
| 01/21/2026 | Contractor with active Arizona Contractor's License for specified scope of work, or a signed Owner Builder Affidavit is required prior to issuance of permit. The Affidavit form is available at https://www.tucsonaz.gov/Departments/Planning-Development-Services/Permits/Residential-Permits. Contractor or Owner must have a TDC Online account and be added to the permit as the correct contact type https://www.tucsonaz.gov/files/sharedassets/public/v/2/pdsd/documents/tdc-faq/new-pdfs/adding-additional-contacts.pdf. If you are providing an Owner Builder Affidavit, the owner MUST be attached as a contact on the permit. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0126-00263
Permit Description: REV_1, Equipment relocation; Installation of 9.02 kW PV System with SE battery and 225A MPU
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/29/2026 | BULD - Electrical Clearance | Passed | 4.29.26 Approved for DGC/bat |
|
| 04/29/2026 | RSBU - Building Final | Passed | ||
| 04/29/2026 | COT - RSOL - Electrical Final Solar Project | Passed |