Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-RES-0125-00054
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
31 S GOLD MINE LP
Address NEW:
31 S GOLD MINE LP
Apply Date:
01/06/2025
Applicant:
TFS Solar
Description:
Roof mount 9.46kW DC photovoltaic solar system; 22 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 3 strings. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup. NEMA 14-50 EV Charger outlet with GFCI.
Permit Reviews
Permit Number - TC-RES-0125-00054
Permit Status: Complete
Permit Description: Roof mount 9.46kW DC photovoltaic solar system; 22 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 3 strings. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup. NEMA 14-50 EV Charger outlet with GFCI.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/07/2025 | RESIDENTIAL SOLAR v.1 | 02/05/2025 | APPROVED |
Completed Inspections
Permit Status: Complete
Permit Number: TC-RES-0125-00054
Permit Description: Roof mount 9.46kW DC photovoltaic solar system; 22 modules; 13.5 kWh Storage, 1 Tesla Powerwall-3 battery with integrated PV inverter with 3 strings. 200A bus with 200A MCB, interconnection via PCS, Tesla Backup Switch for whole home backup. NEMA 14-50 EV Charger outlet with GFCI.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/01/2025 | BULD - Electrical Clearance | Passed | Approved solar and powerwall 3 - DGC/BAT Clearance to TEP is required for the solar meter | |
| 04/01/2025 | RSBU - Building Final | Passed | ||
| 04/01/2025 | COT - RSOL - Electrical Final Solar Project | Passed |