Permit: TC-RES-0124-00005
Permit Details
Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address:
2915 E FLORENCE DR
Address NEW:
2915 E FLORENCE DR
Apply Date:
01/02/2024
Applicant:
Christopher Ortiz Y Pino
Description:
Master Suite Addition
Permit Reviews
Permit Number - TC-RES-0124-00005
Permit Status: Inspections complete
Permit Description: Master Suite Addition
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/08/2024 | RESIDENTIAL NEW DWELLING v.2 | 05/06/2024 | APPROVED |
| 07/23/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/25/2024 | APPROVED |
| 01/02/2024 | RESIDENTIAL NEW DWELLING v.1 | 01/24/2024 | REQUIRES RESUBMIT |
| 10/01/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/01/2024 | APPROVED |
Conditions
Permit Number - TC-RES-0124-00005
Permit Status: Inspections complete
Permit Description: Master Suite Addition
| Date | Description | Comments |
|---|---|---|
| 04/23/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
| 10/01/2024 |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0124-00005
Permite Description: Master Suite Addition
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/18/2024 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
| 09/27/2024 | COT - RSME - Mechanical Final | N/A | Partial Pass | |
| 12/18/2024 | COT - RSPL - Plumbing Final | N/A | Partial Pass | |
| 12/18/2024 | RSBU - Building Final | N/A | Not Ready |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-RES-0124-00005
Permit Description: Master Suite Addition
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/28/2024 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
| 05/29/2024 | COT - RSBU - Preslab | Passed | ||
| 05/29/2024 | COT - RSEL - Grounding/Bonding | Passed | ||
| 05/29/2024 | COT - RSPL - Rough Soil | Passed | ||
| 06/28/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 06/28/2024 | COT - RSBU - Roof Nailing | Passed | ||
| 09/27/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 10/18/2024 | BULD - Electrical Clearance | Passed | requires bonding | |
| 12/18/2024 | COT - RSEL - Electrical Final | Passed | ||
| 02/07/2025 | COT - RSEL - Outdoor Lighting | Passed | ||
| 02/07/2025 | COT - RSME - Mechanical Final | Passed | ||
| 02/07/2025 | COT - RSPL - Plumbing Final | Passed | ||
| 02/10/2025 | RSBU - Building Final | Passed |